Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 7
Total 1337 questions

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

What communication methods would a project manager use for overall effective project communication?

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?

A.

Project charter

B.

Product roadmap

C.

Project management plan

D.

Product requirements

What is one reason why stakeholders must be identified when performing business analysis?

A.

To identify project timelines through business reviews

B.

To allow the business analyst to determine the project budget

C.

To identify who should define the business requirements for the project

D.

To determine a cost-benefit analysis for the project

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?

A.

The project is over budget and behind schedule.

B.

The project is over budget and ahead of schedule.

C.

The project is under budget and behind schedule.

D.

The project is under budget and ahead of schedule.

Which is the appropriate tool to identify the possible correlation two elements in aprocess?

A.

Scatter diagram

B.

Cause and effect diagram

C.

Histogram

D.

Control charts

A project manager has been assigned to a project with a short duration and given funding to form a small team. The project manager needs to choose team members based on their availability and other aspects.

What other features should the project manager consider?

A.

Skill set, expertise, and training readiness

B.

Past project performance, wage rate, and network base

C.

Collaborative skills, quality focus, and political connections

D.

Priorities, resource demand, and expertise

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?

A.

SAFe®, as it does not allow for scaling work across different teams in the organization.

B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.

C.

Kanban, because the team does not start new work until the existing work is finished.

D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Which of the following is an example of schedule compression?

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

A.

Project

B.

Functional

C.

Program

D.

Portfolio

While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)

A.

Project sponsor

B.

Portfolio manager

C.

End user

D.

Program manager

E.

Internal inspector

Make-or-buy analysis is a tool and technique of which process?

A.

Conduct Procurements

B.

Plan Procurement Management

C.

Analyze Procurements

D.

Control Procurements

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

A.

Team velocity in past iterations

B.

Related epics of each story

C.

Product owner ' s priorities

D.

Detailed acceptance criteria

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

A.

-9

B.

37

C.

9

D.

322

Howls program success measured?

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-etfectiveness. and customer saDstaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

What process in Project Risk Management prioritizes project risks?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Responses

D.

Implement Risk Responses

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

The Agile principle " welcome changing requirement, even late in development " relates to which agile manifesto?

A.

Working software over comprehensive documentation

B.

Individuals and interactions over processes and tools

C.

Customer collaboration over contract negotiation

D.

Responding to change over following a plan

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

Which of the following does a portfolio combine?

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

What tool or technique will establish expected behaviors for project team members?

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

A method to manage stakeholder expectations in the scope statement is to clearly:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Which three techniques can be estimate costs?

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

The Plan Stakeholder Management process belongs to which Process Group?

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Page: 7 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved