CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
What communication methods would a project manager use for overall effective project communication?
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
What is one reason why stakeholders must be identified when performing business analysis?
In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?
Which is the appropriate tool to identify the possible correlation two elements in aprocess?
A project manager has been assigned to a project with a short duration and given funding to form a small team. The project manager needs to choose team members based on their availability and other aspects.
What other features should the project manager consider?
The project manager is creating the communications management plan Which group of inputs Is required to begin?
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.
Which method should be used in this situation?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take to account for risk management n this environment’
Plan-do-check-act is also known as:
Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
Which of the following is an example of schedule compression?
Reserve analysis is a tool and technique used in which process?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap. Which three roles are involved in establishing the product roadmap? (Choose three)
Make-or-buy analysis is a tool and technique of which process?
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?
A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.
What is the SV?
Howls program success measured?
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
An intentional activity to modify a nonconforming product or product component is called:
What process in Project Risk Management prioritizes project risks?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
The Agile principle " welcome changing requirement, even late in development " relates to which agile manifesto?
A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?
Which of the following does a portfolio combine?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
What tool or technique will establish expected behaviors for project team members?
Which of the following is a tool and technique used to monitor risk?
A method to manage stakeholder expectations in the scope statement is to clearly:
Which three techniques can be estimate costs?
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?
The Plan Stakeholder Management process belongs to which Process Group?


