Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 7
Total 1320 questions

Which activity involves ensuring that the composition of a projects configuration items is correct?

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.

What should the project manager do next?

A.

Update the project management plan.

B.

Add the discovery to the assumptions.

C.

Evaluate the risk with the project team.

D.

Conduct an opportunity analysis with the team.

Select three processes that are associated with Project Schedule Management.

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

During which process does the project team receive bids and proposals?

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

The review of a seller ' s progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

What is the equation to calculate cost variance (CV)?

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Which of the following reduces the probability of potential consequences of project risk events?

A.

Preventive action

B.

Risk management

C.

Corrective action

D.

Defect repair

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Identify Risks is part of which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Which enterprise environmental factors may influence Plan Schedule Management?

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

What are the project management processes associated with project quantity management?

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

A method to manage stakeholder expectations in the scope statement is to clearly:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.

How should the project manager report the status of the project?

A.

The project is at risk as the cost variance (CV) is negative.

B.

The project is within budget and within schedule.

C.

The project is within budget but is delayed.

D.

The project is tracking well as the cost variance (CV) is negative.

When is a project finished?

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Which of the following is a tool or technique used in the Determine Budget process?

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Which technique is utilized in the Control Schedule process?

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Which factors should be considered for cross-cultural communication?

A.

Background, personality, and communications management plan

B.

Personality, background, and escalation process

C.

Sponsor relationship, personality and background

D.

Current emotional state, personality, and background

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

What purpose does the hierarchical locus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Which tool or technique is used in the Develop Project Management Plan process?

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Project contracts generally fall into which of the following three broad categories?

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

An input to the Plan Stakeholder Management process is:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Which role does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Who defines the scope of the product

A.

The client

B.

The project manager

C.

The team

D.

The program manager

Change requests are processed for review and disposition according to which process?

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Which of the following is a goal of the project charter?

A.

Detail requirements for the project tasks.

B.

Empower the project manager to manage the project.

C.

List all tasks the team should perform in the project.

D.

Develop a business case to support the project.

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Page: 7 / 7
Total 1320 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved