Prepare effectively for your PMI PMI-002 Certified Associate in Project Management (CAPM) Certification certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 8 / 8
Total 748 questions

A leadership style in which the project manager shares problems with team members and formulates solutions as a group is called _________.

A.

Autocratic

B.

Consultation In a group

C.

Consensus

D.

One-to-one consultation

Ideally, resource levelling should be limited to activities ________.

A.

With negative float

B.

Witn zero float

C.

0n tne critical path

D.

With positive float

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called __________.

A.

Negotiation

B.

Arbitration

C.

Smoothing

D.

Forcing

The communications management plan is primarily dependent on the ____________.

A.

Length of the project

B.

Physical location of team members

C.

Specific needs of the project

D.

Project deliverables

The independence of two events in which the occurrence of one is not related to the occurrence of the other is called _______.

A.

Event phenomenon

B.

Independent probability

C.

Statistical independence

D.

Statistical probability

Estimate Costs_____________.

A.

Involves developing an estimate of the costs of the resources needed to complete project activities

B.

Cost estimates are generally expresses in unit of some currency.

C.

Involves allocating the overall estimates to individual work items

D.

All of the above

Which of the following statement is true about Quality control?

A.

Monitoring specific project results to determine If they comply with relevant quality standards

B.

Evaluating overall project performance on a regular basis

C.

Taking action to increase the effectiveness and efficiency of the project

D.

Identifying which quality standards are relevant to the project

You are project manger of an existing project. You have been with your company for several years but not in the area where this project is occurring. A Project Management Plan is in place. The project has not exceeded many baseline change thresholds. The customer is not happy with the status of the project. Which of the following is the BEST initial action?

A.

Prepare a corrective action plan

B.

Conduct team-building with all stakeholders

C.

Verify the customer's needs and expectations

D.

None

The work that must be done in order to deliver a product with the specified features and functions is called __________.

A.

Product scope

B.

Staffing scope

C.

The project

D.

Project scope

To shorten project duration, resources have been added to tasks on the critical path. The plan should then be reviewed for the __________.

A.

Lagging time on other paths

B.

Emergence of a new critical path

C.

Resource assigned to other tasks on the critical path

D.

Longest task remaining in the plan

Complete final contract performance reporting and verify product is done in _______.

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Management reserves are used to handle which type of risk?

A.

Unknown unknowns

B.

Known unknowns

C.

Business risks

D.

Pure risks

A project manager's role is likely to be part-time in which of the following organizations?

A.

Weak matrix

B.

Projectized organization

C.

Balanced matrix matrix

D.

All of the above

What impact does a matrix organization have on project team development?

A.

No impact at all

B.

It complicates team development

C.

It simplifies team development

D.

It hinders team development completely