Prepare effectively for your PMI PMI-002 Certified Associate in Project Management (CAPM) Certification certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Market conditions are a part of ________.
The project management plan:
Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?
Which of the following is not part of project scope management?
You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?
Who is responsible for issuing the project charter?
Assumptions in the project plan should be _________.
What is the communication channel delta if the members in the communication plan are increased from 5 to 10?
The activity that is most concerned with the current status of the project schedule is called ___________.
If a project with a CPI of 1.6, what you tell?
Administrative Closure should occur ___________.
What are the outputs of Initiation process?
Make-or-buy decisions measure the costs of both options. What are the two options?
Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
How many communication channels will be required in a project in which 5 individual are participating?
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
If a project with a SPI of 0.8, what you tell?
What are the inputs for Initiation process?
Which of the following is not a form a leadership power?
You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:
Administrative closure is the process that ________.
How many communication channels will be required in a project in which 10 individual are participating?
You are project manager of a project, which of the following is not your responsibility?
Which of the following does not provided by scope statement?
When the version control numbers should change?
Which of the following is true about pure risk?
Human resource adininistration is the primary responsibility of the_____________
The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called _________.
On any project, who creates the Lessons Learned document?