Prepare effectively for your PMI PMI-100 Certified Associate in Project Management (CAPM)® certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
The scope management plan and scope baseline are contained in:
The following is a network diagram for a project.
What is the critical path for the project?
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
The purpose of developing a project scope management plan is to:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
In complex projects/ initiating processes should be completed:
Through whom do project managers accomplish work?
Project management processes ensure the:
Which term describes an assessment of correctness?
The following is a network diagram for a project.
The free float for Activity H is how many days?
The primary benefit of the Plan Schedule Management process is that it:
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
Which item is a cost of conformance?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
The following is a network diagram for a project.
The free float for Activity E is how many days?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Which tool or technique is required in order to determine the project budget?
Which type of graphic is displayed below?
Which tools or techniques are used during the Close Project or Phase process?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?