PMI-100 PMI Certified Associate in Project Management (CAPM)® Free Practice Exam Questions (2025 Updated)
Prepare effectively for your PMI PMI-100 Certified Associate in Project Management (CAPM)® certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which of the following is a group decision-making technique?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
Which of the following is an output of Close Procurements?
Which technique is utilized in the Control Schedule process?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
Which baselines make up the performance measurement baseline?
The total of the planned value (PV) is also known as:
Which of the following is an output of the Conduct Procurements process?
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which of the following is a tool and technique used to monitor risk?
The process to ensure that appropriate quality standards and operational definitions are used is:
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Which of the following is a tool or technique used in the Acquire Project Team process?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Resource calendars are included in the:
The initial development of a Project Scope Management plan uses which technique?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The process of identifying specific actions to be performed to produce project deliverables is:
What is project management?
The staffing management plan is part of the:
Who determines which dependencies are mandatory during the Sequence Activities process?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Perform Quality Control is accomplished by:
When is a project finished?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?