PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 8
Total 476 questions

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?

A.

Report this as a blocker and ask senior management to provide the right subject matter experts (SMEs) until all the outstanding issues can be dosed.

B.

Identify the key business stakeholders and invite them to day-long sessions until all the dependencies and outstanding issues can be closed.

C.

Identify the key dependencies that need to be resolved in order of priority level so the user stories can meet the definition of ready (DoR) criteria.

D.

Report this as a blocker and ensure the product owner is able to deprioritize the issues so the user stories can meet the definition of ready (DoR) criteria.

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

A.

Escalated the issue to management

B.

Ensured the early engagement of key stakeholders

C.

Provided feedback to the architecture team to change the enterprise architecture standards

D.

Raised an exception for non-adherence to the enterprise architecture standards for this product

What should the team do to improve the accuracy of their estimates?

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

D.

Begin tracking estimated effort metrics as an input to performance evaluation

What is the first thing an agile development team should do when planning an iteration?

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.

What should the project team adopt to address this issue and improve task flow, considering all the demands?

A.

Increase the number of items allowed in the 'In progress" column to accommodate the high volume of tasks and provide flexibility.

B.

Limit the work in progress (WIP) and implement strict policies to encourage team members to focus on completing existing tasks before starting new ones, ensuring a balanced workload.

C.

Move tasks to the 'Done" column regardless of their completion status to give the appearance of progress and alleviate the pressure of the backlog.

D.

Add more team members with varying levels of expertise to handle the increased workload, aiming to accelerate task completion and reduce the backlog in the 'In progress" column.

What should the agile team lead do?

A.

Create a central repository for information, and provide access to Team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide Team B with the information on an "as needed" basis

What should an agile practitioner do?

A.

Present opportunities in order to be supportive and grow that team member's talents.

B.

Encourage the team member to fit in more with the established team norms.

C.

Bring this to management's attention so they don't disrupt the team.

D.

Ask the team member to respect defined roles on the project to avoid confusion with the team.

A senior executive contacted an agile lead about starting an agile project to solve a problem for the human resources (HR) department of a company. The project idea is not clear and no backlog has been developed.

How should the agile lead start the project?

A.

More work is needed to refine the idea and there is no backlog to start working on, so there is no way to help the manager.

B.

Identify the persona that needs help and conduct a workshop applying the empathy map technique about that persona.

C.

Review how similar problems have been resolved in other companies and see if a solution is available on the market.

D.

Start working on a list of user stones to create a backlog and suggest a product owner be assigned to the project.

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

What can an agile practitioner conclude about team A and team B's estimates?

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.

What should the agile coach do?

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team's time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

What should the product owner do?

A.

Accept responsibility for the product's delay.

B.

Ensure that the project sponsor's priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?

A.

Note the changes to the restructure and roles that affect team activities

B.

Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements.

C.

Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project

D.

Obtain a copy of the redefined key roles to update the stakeholder analysis

Several team members have complained to senior management about their Scrum Master's processes. What should the Scrum Master do to address the team's process concerns?

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stories based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

How should an agile project leader interact with the Product Owner?

A.

Conduct regular one-on-one meetings to review development features and trace them back to the product roadmap

B.

Ensure that they attend regular sprint meetings to provide product-feature feedback

C.

Share any new versions of the project plan with them including updated statuses for tasks and project milestones

D.

Schedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints

Page: 5 / 8
Total 476 questions