Prepare effectively for your PMI PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 8 / 8
Total 481 questions

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team ' s historical velocity to calculate a range of features that can be delivered

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.