Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 4
Total 264 questions

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

A.

Industry's standard procedures

B.

Current request for proposal (RFP)

C.

Company's historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations 

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

A.

Provided regular training to the risk owners for plan implementation

B.

Determined risk triggers and thresholds in the risk response plan

C.

Increased communications to influence stakeholder risk responses

D.

Updated the project schedule, adding risk owner implementation tasks.

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase. The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded.

Which analysis should the risk manager perform to demonstrate this to the stakeholders'?

A.

Monte Carlo analysis

B.

Pareto analysis

C.

Ishikawa analysis

D.

Qualitative risk analysis

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

A.

Meet with the project team to brainstorm potential solutions to the problem.

B.

Implement the risk response plan to remedy the problem as soon as possible.

C.

Initiate discussions with the project manager to decide how to manage the problem.

D.

Escalate the problem to the project sponsor to agree on the best course of action. 

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented. 

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?

A.

During the Plan Risk Management process

B.

Once all individual risks have been scored

C.

After risks have been identified by stakeholders

D.

Once the overall project risk has been estimated

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

During project development, a risk manager notices that a major update in the country's regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

A.

Sensitivity analysis

B.

Threshold analysis

C.

Reserve analysis

D.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis 

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

A.

Perform a probability and impact assessment

B.

Perform Monte Carlo simul-ations

C.

Perform a sensitivity analysis

D.

Perform a risk data quality assessment

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

A.

Document the risks and response actions in a clear manner.

B.

Communicate with the project manager on the topic.

C.

Assign owners who will be fully accountable to managing the risks.

D.

Define the response plans and take the lead in implementing them.

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simul-ation

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

A.

Update the watchlist.

B.

Initiate a risk response when these risks occur.

C.

Address only the high-priority risk.

D.

Perform a risk urgency assessment. 

Page: 1 / 4
Total 264 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved