Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 5
Total 333 questions

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented. 

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

A.

Engage with the team to present the actual results to the sponsor.

B.

Prepare a management of change (MOC) to adjust the project cost and duration.

C.

Move forward with the lessons learned from the sprint.

D.

Review the assumptions to understand any change.

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

An international telecommunications company is preparing to launch a new service across multiple regions. The project team is concerned about the varied technical issues and regulatory challenges in each region. The risk manager is tasked with identifying and analyzing risks to prioritize them based on their potential impact.

Which two actions should the risk manager take? Choose two.

A.

Assign risks to the most tenured team members for assessment.

B.

Engage with local experts to understand region-specific constraints.

C.

Model one region and then follow the same strategy in all regions.

D.

Apply a common risk matrix across all regions.

E.

Develop a customized risk matrix for each region.

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

A.

Budget variance data from previously completed projects.

B.

Project scope and cost management plans from previous projects.

C.

Lessons learned from similar completed projects.

D.

Previous project risks that may be relevant to this project.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team ' s tasks have yet to be completed.

What should the risk manager do next?

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

In reviewing the team ' s identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project ' s incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

A.

Exploit

B.

Accept

C.

Share

D.

Enhance 

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project ' s key stakeholders.

What is the first resource the project manager should reference?

A.

Benefits management plan

B.

Enterprise environmental factors (EEFs)

C.

Project charter

D.

Requirements management plan

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

A.

Stakeholder management and communication tools

B.

Team performance reports and analysis tools

C.

Schedule management tools (i.e., Gantt Charts)

D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

A.

Brainstorming

B.

Delphi method

C.

Focus group

D.

Checklist analysis

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

A.

Update the assumptions/exclusions register

B.

Hire more resources and crash the schedule

C.

Perform a qualitative risk analysis for the project

D.

Mitigate risks identified on the sensitivity analysis

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

D.

Communicated better with the organization ' s CEO.

Which statement describes the risk portrayed on the risk matrix heat map below?

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

A.

Quantitative risk analysis

B.

Force field analysis

C.

Qualitative risk analysis

D.

Stakeholder analysis

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

A.

Implement a strict, standardized approach to ensure consistency across all regions.

B.

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.

Adopt a fully flexible approach that allows teams to manage issues based on local context.

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Page: 1 / 5
Total 333 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved