Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (PMBOK 7th Version) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMP Project Management Professional (PMBOK 7th Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 10 / 11
Total 2191 questions

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a

specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted

the import of this machine model.

What should the project manager have done to prevent this from happening?

A.

Ensured that the SMEs correctly defined the project scope and the machine model.

B.

Ensured the project sponsor provided enough funding to purchase the latest version of the machine.

C.

Ensured that regulatory compliance was considered in the quality management plan.

D.

Ensured that the technical team researched and selected the latest model of the machine.

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second

iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.

What should the project manager do?

A.

Ask the product owner to add the missing feature in the backlog.

B.

Invite stakeholders to discuss the impact of adding the regulatory feature.

C.

Estimate the related cost and ask for a project extension.

D.

Increase the capacity of the team to include the missed feature.

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully. What should the project manager do to reduce the risk of project failure?

A.

Ask the sponsor to add experienced professionals to the team.

B.

Assign a dedicated resource to check the quality of each deliverable.

C.

Approve the appropriate training program for team members.

D.

Provide team members with the necessary coaching and mentoring.

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites,

the office, and remote locations. In addition, some team members have limited access to the electronically shared files.

How should the project manager manage this challenge?

A.

Request changes in the processes since it is not suitable for the company environment.

B.

Communicate a strong message to the team explaining the importance of knowledge transfer.

C.

Study the environment and the available resources to determine which approach to use.

D.

Send the intended information through email since it is the primary communication tool.

As part of its growth strategy, management is providing all of its ongoing projects with junior employees and is requesting experienced team members to mentor them. The experienced employees argue that the mentoring program will not add value to their projects and will limit their ability to deliver.

How should the project manager handle this situation?

A.

Recommend to management that the junior employees should receive formal training and courses.

B.

Schedule time with all of the project team members since it is the role of the project manager to mentor the team.

C.

Allocate specific time for experienced team members to mentor the junior employees.

D.

Assign an instructor to mentor the junior employees so that the experienced team members can focus on project tasks.

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.

B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.

C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.

D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

A.

Ask the Scrum team members to share retrospectives.

B.

Ask the scrum master to attend the workshops.

C.

Invite the Scrum team members as optional participants.

D.

Invite the Scrum team members as mandatory participants.

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.

What should the project manager do to keep the stakeholders engaged?

A.

Use email as a communication channel.

B.

Use feedback and decision-making tools.

C.

Use meetings as a communication channel.

D.

Use a shared collaboration platform.

In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.

What should the project manager have done to avoid this situation?

A.

Selected countries that had similar regulatory requirements.

B.

Asked procurement to assign resources located in each country.

C.

Managed risk mitigation strategies specific to each country.

D.

Identified the regulatory differences among the countries.

A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.

What should the new project manager do first?

A.

Review the business case to gather information about the project.

B.

Initiate a rebaselining of the project based on the project sponsor's concerns.

C.

Discuss the items in the requirements register with the project team.

D.

Meet with the project stakeholders to understand the project sponsor's concerns.

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

A.

Risk to delivery

B.

Technical complexity

C.

Business value

D.

Estimation accuracy

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

A.

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.

Reschedule the kick-off meeting for the following month so all can attend on-site.

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

A.

Test product integration in accordance with the requirements.

B.

Evaluate the quality checklist for product compliance.

C.

Review the approved exit criteria for the product.

D.

Verify the production budget before advancing the product.

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

A.

Clear responsible, accountable, consult, and inform (RACI) matrix

B.

Risk management and issues resolution plan

C.

Resource management and conflict resolution plan

D.

Clear project work breakdown structure (WBS) and timeline

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.

What should the project manager do first?

A.

Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.

B.

Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.

C.

Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

A.

The customer's requirements should have been captured in order to meet the customer's standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer's requirements should have been captured and modified to meet the supplier’s standards.

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?

A.

Send the new representative the approved project management and communications management plans.

B.

Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.

C.

Meet with the project sponsor to discuss how to incorporate the new representative in the project.

D.

Meet with the new representative to determine their understanding of the project and address their concerns.

A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project

manager do first to address this situation?

A.

Try to remove the barriers and empower team members.

B.

Ask the organization to improve the internal procedures.

C.

Train the team members on the organization's procedures.

D.

Discuss the issue in the next sprint review meeting.

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

A.

Use a servant leader approach.

B.

Assume the functional manager role.

C.

Perform the project sponsor activities.

D.

Act as the project owner.

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to

analyze team performance? (Choose two)

A.

0Project schedule

B.

Product backlog bumup chart

C.

Work breakdown structure (WBS)

D.

Cumulative flow diagram of completed features

E.

Burndown chart

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

A.

Reach an agreement with the team on how to handle the situation.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Convince the team member not to leave until the project is completed.

A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those

times, the interactions and work as a team are reduced and ineffective.

What should the project manager do?

A.

Inform the team members who are joining late to join early and work together.

B.

Allocate the overlap time for each team member and ask them to adhere to the schedule.

C.

Ask the team to define a team charter and agree on core working hours.

D.

Ask the team to start at the same time to obtain the maximum number of team working hours.

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

A.

Organize an online distribution channel from another country.

B.

Ask the sponsor to authorize the launch and then wait for approval.

C.

Ask the board to use their influence and speed up the approval.

D.

Work with the team to find ways to bypass the regulations.

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

A.

Defined acceptance criteria in a quality checklist agreed upon before starting the build phase

B.

Approved a detailed change management process before starting the build phase

C.

Provided compensation for issues due to the variance in the agreed-upon requirements

D.

Continuously communicated the changes in the work plan and the agreement to the client

A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?

A.

Send a detailed email with the completed design document.

B.

Conduct a workshop with all of the stakeholders.

C.

Conduct a workshop with both of the teams.

D.

Upload the design documents into the project repository.

A project manager is leading a project in a heavily regulated industry. Match the considerations on the left with the correct compliance plan categories on the right.

A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users.

What should the project manager do?

A.

Ensure that the user guide is detailed and has clear instructions.

B.

Ensure that comprehensive documentation is handed over.

C.

Ask the project team to provide operational support for 1 year.

D.

Ensure that knowledge is transferred to the operations team.

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.

What should the project manager do?

A.

Change the project methodology in order to achieve completion of the deliverable within 2 months.

B.

Advise the sponsor that it is not the project manager’s job to evaluate the project.

C.

Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.

D.

Use the management reserve in order to expedite completion of the deliverable within 2 months.

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

A.

Review the risk register and assign functional managers as resources.

B.

Analyze the resource pool and assign internal resources who participated in past projects.

C.

Perform an analysis of the key cost drivers and present alternatives.

D.

Review the work breakdown structure (WBS) to ensure there are adequate resources.

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.

Obtain approval from the project team and add the new story to the product backlog

C.

Receive an agreement from the product owner and add the new story to the product backlog

D.

Negotiate with the scrum master before adding the new story to the sprint backlog

A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.

How can the project manager address this challenge to assure outsourced vendors deliver?

A.

Review the coordination and communication costs with the supplier.

B.

Develop a new strategy for communication and management of resources.

C.

Review the risk management plan for the mitigation activities.

D.

Submit a change request to increase the contingency budget.

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors.

What should the project manager do to ensure the successful execution of the project?

A.

Perform procurement control checks throughout the project

B.

Activate the mitigation plan for the procurement risks

C.

Oversee the selection process for the vendor to procure the needed products and services

D.

Ask the procurement department to select the vendor using established processes

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

A.

Have the team complete the technically complex story first.

B.

Work with the product owner to clarify and prioritize the backlog stories.

C.

Have the team complete the less complex story first.

D.

Work with the agile coach on the user stories to avoid conflict.

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

A.

Refer to the requirements traceability matrix and analyze the requirement.

B.

Analyze the benefits management plan and implement the needed change.

C.

Consult the scope management plan with the customer to understand the gap.

D.

Discuss and agree with the customer to implement the missing requirement.

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

A.

Project requirements, target benefits, issue log, metrics

B.

Target benefits, strategic alignment, time frame for realizing benefits

C.

Strategic alignment, benefits owner, risk register

D.

Target benefits, benefits owner, lessons learned

A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.

Which approach should the project manager use as a servant leader?

A.

Ask stakeholders to find and self-fund education about this new technology.

B.

Allocate resources to provide training about the new technology to the stakeholders.

C.

Contact the project sponsor to get those stakeholders removed from the project.

D.

Escalate the issue with upper management to find a novel solution for this situation.

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as

a whole is low, especially in terms of group activities.

What should the project manager do?

A.

Negotiate for new team members.

B.

Review and update the communications management plan.

C.

Review and reassign team assignments.

D.

Facilitate communication and team building.

A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.

What should the project manager do?

A.

Remove the development team's rejected feature from the backlog.

B.

Reassure all team members that the development team will fix the issue.

C.

Initiate an improvement plan for the development team to follow.

D.

Evaluate the context for the conflict with the development team.

A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.

What should the project manager do?

A.

Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.

B.

Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.

C.

Seek key stakeholders' approval and finalize the budget with the reserve.

D.

Agree with the project sponsor and finalize the budget without the reserve.

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

A.

Share a work performance report with the team member's supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

A.

Register the issue as a risk with the project team members.

B.

Review the project schedule with project team members and the suppliers.

C.

Advise the procurement department to develop a new supplier strategy.

D.

Use the procurement and risk management plans to manage this issue.

A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?

A.

Allocate additional resources to the development team to ensure the original scope can be completed on time.

B.

Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

C.

Agree on reducing the scope to match the team's resources and plan to add the removed items to future sprints.

D.

Insist on keeping the original scope and explain the importance of meeting all the project milestones on time.

A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.

What should the new project manager do first?

A.

Meet with the team and gather their input on the completion rate.

B.

Revisit the timelines of the deliverables and the project.

C.

Consult the sponsor and secure approval to complete the project.

D.

Transition to an agile delivery so project closure will be faster.

During a project's stakeholder identification stage, team members are struggling to identify the level of influence for two stakeholders. One is considered important, while the second is not quite as important as the first one. For this project, stakeholder engagement is a critical activity.

What should the project manager do?

A.

Move forward due to time constraints.

B.

Call a meeting with the project team to decide.

C.

Consider both of them to be important stakeholders.

D.

Conduct an evaluation on both stakeholders.

A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?

A.

Ask the team member to contact the learning and development team for additional help.

B.

Share the required documents with the team member.

C.

Arrange a required training session for the team member.

D.

Raise this issue in the next team meeting and ask the rest of the team to clarify.

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

A.

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.

Ask the functional lead to remove this additional step as it is not vital to the project.

D.

Advise the team that the functional lead's preference should be taken into consideration.

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Page: 10 / 11
Total 2191 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved