Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 9 / 10
Total 1988 questions

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

A.

Request that the vendor provides a manual with all required knowledge

B.

Implement retrospectives with the vendor to gather the required knowledge

C.

Submit a change request to extend the vendor's contract to provide formal training for the team

D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)

assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.

B.

Organize a formal session led by a skilled facilitator with defined rules for how

participants will interact with one another.

C.

Distribute a questionnaire on the key features of the product and encourage the teams

to respond with their design recommendations.

D.

Hold multiple sessions of manageable sizes with participants from both teams to

discuss their ideas.

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

A.

Updated the stakeholder engagement plan to reflect a change in the product owner

B.

Communicated the status of the project more frequently with the product owner

C.

Updated the communications management plan to reflect a change in the communication needs

D.

Reevaluated the new product owner's needs for better engagement

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

A.

Submit a change request to adapt the objectives of the project to the current situation

B.

Ask the scrum master to refine the user stones to improve the team members' understanding

C.

Find and provide training to the project team members who do not have the required skills

D.

Extend the duration of standup meetings to include skill transference from trained to untrained members

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

A.

Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

B.

Ask the sponsor for support regarding the allocation of additional resources to finish on time.

C.

Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources.

D.

Meet with the customer to agree on the components of the solution and the priorities.

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?

A.

Monitored progress in achieving the business value throughout the project

B.

Asked for additional time to achieve the project goals and increase business value

C.

Increased the number of project resources to ensure attainment of the business value

D.

Reviewed previous projects’ lessons learned and applied them to this project

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact to

the project value.

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

A.

Share project documentation in a repository with exclusive access.

B.

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.

Send periodic emails to senior management with the latest project updates.

D.

Keep project artifacts up-to-date and accessible to all stakeholders.

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Page: 9 / 10
Total 1988 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved