Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 6
Total 594 questions

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization

and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

A.

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B.

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C.

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D.

Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.

A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.

What should the project manager do?

A.

Use the contingency budget to implement compression techniques to finish the current project phase early.

B.

Review the stakeholder engagement plan and determine the best course of action to take.

C.

Notify the outgoing sponsor that the project needs to be put on hold until the new sponsor is onboarded.

D.

Submit a change request to the change control board (CCB) to modify the end date of the current phase.

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.

What should the project lead do?

A.

Ask the developers to use peer programming.

B.

Build a task board on a large wall using sticky notes.

C.

Build a detailed schedule and describe each task in detail.

D.

Ask the product owner to reprioritize the backlog.

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

A.

Ask the Scrum team members to share retrospectives.

B.

Ask the scrum master to attend the workshops.

C.

Invite the Scrum team members as optional participants.

D.

Invite the Scrum team members as mandatory participants.

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors.

What should the project manager do to ensure the successful execution of the project?

A.

Perform procurement control checks throughout the project

B.

Activate the mitigation plan for the procurement risks

C.

Oversee the selection process for the vendor to procure the needed products and services

D.

Ask the procurement department to select the vendor using established processes

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.

What should the project manager do first?

A.

Conduct a root cause analysis (RCA) and plan the correct actions to ensure completion of the tasks on time.

B.

Allocate another resource to help the team member to complete the tasks and meet the estimated activity time.

C.

Train the team member in the methodology to get the sufficient knowledge to meet the estimated activity time.

D.

Apply crashing to the strategic tasks to recover any time that was lost to bring the project on track.

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

A.

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.

Reschedule the kick-off meeting for the following month so all can attend on-site.

A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?

A.

Provide the HR review team with the team norms document.

B.

Invite the HR review team to attend one of the daily standup meetings.

C.

Discuss the resource management plan with the HR review team.

D.

Direct the HR review team to the communications management plan.

In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.

What should the project manager do?

A.

Invite team members to volunteer for roles for which they feel qualified.

B.

Revoke the delegated responsibilities to keep the team members harmonious.

C.

Remind team members that administrative decisions are the project manager's duties.

D.

Explain the rationale for delegating responsibilities to team members.

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

A.

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

B.

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.

C.

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.

D.

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

A.

Analyze the communication needs of the stakeholders.

B.

Communicate the project details to the stakeholders.

C.

Communicate progress more frequently to the stakeholders.

D.

Introduce a separate stakeholder engagement meeting.

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?

A.

Meet with the vendors to evaluate the impact on the budget.

B.

Implement crashing to mitigate the impact on the budget.

C.

Review the organizational process assets (OPAs) as a reference.

D.

Request the release of management reserve for the project.

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager's knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.

B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.

C.

Review the project approval requirements in the project charter and confirm who will be approving the project.

D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.

Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.

What should the project manager do first to finalize the schedule?

A.

Engage the two team members to investigate the reasons each believes that their documents are correct.

B.

Update the schedule so it is available for team members to continue the work and figure out the discrepancy later.

C.

Ask the two team members to meet to work the discrepancy out and let the project manager know the outcome.

D.

Ask the team members to send the documents and apply expert judgment to update the schedule.

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

A.

Allow the team to proceed as they attempt to meet the timeline.

B.

Add a subject matter expert (SME) to the project team.

C.

Invite stakeholders to discuss a mitigation plan to finish on time.

D.

Fill the skill gap personally to execute the project.

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

A.

Reprioritize the backlog based on value and cost of delay divided by duration.

B.

Switch to a predictive approach to prevent any further delays to completion.

C.

Reprioritize the backlog based on story size and competence availability.

D.

Remove low-value items from the backlog to compensate for the higher cost.

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

A.

Register the issue as a risk with the project team members.

B.

Review the project schedule with project team members and the suppliers.

C.

Advise the procurement department to develop a new supplier strategy.

D.

Use the procurement and risk management plans to manage this issue.

The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)

A.

Leverage the project governance system to track and manage the project artifacts.

B.

Create a central repository system to assess the effectiveness of the project artifacts.

C.

Review the execution roadmap and ask the legal team to manage the artifacts.

D.

Ensure the project artifacts are kept up to date and accessible to all stakeholders.

E.

Work with the team to determine the process to manage the project artifacts.

Page: 3 / 6
Total 594 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved