Weekend Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: stp75

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (PMP) July 2026 Update Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMP Project Management Professional (PMP) July 2026 Update certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 3
Total 187 questions

A virtual team updates a kanban board weekly with project progress. Recently, team members have raised concerns about properly tracking interdependent activities

How should the project manager address this issue?

A.

Assign one team member as accountable to monitor interdependent activities that are related on an ongoing basis.

B.

Assign activities that are interdependent to the same team members to avoid complexity and ensure progress monitoring.

C.

Adapt the tool for better monitoring and reporting of the interdependent activities’ progress.

D.

Register the issue in the project backlog so that the project team may address it in next iteration.

A project manager is working on a process improvement project. The project team includes stakeholders across all organizational levels from business managers,

process owners to system specialists, and subject matter experts (SMEs). The project is using a hybrid approach. While planning for the next increment, a

disagreement arises between the stakeholders.

What should the project manager do?

A.

Escalate the stakeholders’ conflict to the steering committee to resolve.

B.

Consult with the top tier and influential stakeholders to resolve.

C.

Switch to the predictive methodology for the team to follow an upfront plan.

D.

Meet with the stakeholders privately to identify the areas of conflict.

An engineering consulting firm is hired to support a client in designing technical documents for a new construction site. The project has a tight schedule. The client

does not have a complete scope, but the client cannot wait for the scope to be defined before starting the project.

What should the project manager do?

A.

Start the project and when the scope is defined by the client, update the project schedule accordingly.

B.

Inform the client that the project will not be able to start until the scope is clear and well defined.

C.

Liaise constantly with the client to determine which deliverables are worth developing.

D.

Include the item in the issue log to be frequently monitored in the client ' s weekly meeting.

A project manager has compared the monthly actual costs with the planned costs and estimated the forecast to complete the remaining part of the project. The project

manager realizes that the project will require additional funding.

What should the project manager do first?

A.

Send the new cost estimates and ask the project sponsor to approve them.

B.

Adjust the time and scope to keep the budget unchanged.

C.

Ask the vendor to adjust the time and materials contract to reduce costs.

D.

Assess the budget impact and submit a change request for approval.

A project manager is overseeing a multisprint data integration project involving internal developers and an outsourced analytics team. Midway through the second

sprint, the project manager notices signs of reduced engagement: slower response times, vague status updates, and missed handoff deadlines between the two

teams. The initial project management plan includes regular reporting but no formal feedback mechanisms.

What should the project manager do?

A.

Schedule weekly one-on-one calls with team leads to review task progress.

B.

Launch a retrospective to collect input and uncover team-level issues.

C.

Circulate daily coordination meeting summaries for better visibility.

D.

Ask the sponsor to meet with both groups to reinforce expectations.

An agile project in progress has a large number of blocked items and the project manager does not have visibility on the underlying issues. What should the project manager do to allow transparency and remove the blockers?

A.

Create a shared kanban board for the team to have visibility of the items.

B.

Hold a war room meeting with relevant people to address the blockers.

C.

Change the project status to “on hold” to inform the sponsor about the blockers.

D.

Conduct a retrospective meeting to gain visibility on what is happening.

Due to competing priorities in a project, team members have been working overtime. However, the deadline is still being delayed because of the amount of work

required. The business owner begins questioning the project health and asks for reports on milestones on a weekly basis.

What should the project manager do?

A.

Use the project schedule baseline and a Gantt chart to show actual progress with key milestone dates.

B.

Review the original schedule and calculate the cost performance index (CPI) to show the completed milestones against the planned work.

C.

Submit a change request to update the project schedule and create a Gantt chart for the business owner to view.

D.

Create a visual presentation to demonstrate and justify the possible root cause of the delays for the business owner.

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

In the Health Records Modernization project, stakeholder engagement and management is critical to the successful adoption of the project outcomes. How should the project manager approach management of the various stakeholder communication channels in the complex healthcare project? (Refer to the Health Records Modernization at Hospital Case Study exhibit.)

A.

Establish communication through department leads and request each lead distribute appropriate information.

B.

Simplify communication based on the project management office (PMO) guidance.

C.

Create a tailored communication strategy based on stakeholder analysis and preferences.

D.

Meet with the stakeholders about communication strategy so they can each specify the information they would like to receive.

The project manager of an international marketing campaign is coordinating with global teams and must align activities across several time zones. With such

geographical diversity, what should the project manager do?

A.

Develop a flexible project schedule to incorporate time zone differences, team availability, and cross-regional dependencies.

B.

Prioritize tasks based on the urgency of deadlines and assign to regions with the earliest time zones.

C.

Assign regional leaders to manage local schedules and align their activities with the overall project timeline.

D.

Increase the frequency of virtual meetings to ensure continuous communication and alignment among international teams.

The project manager is leading a project to develop a new product. A representative from the legal team approaches the project team requesting the product go

through a legal review before entering the market. This review would lengthen the schedule and would cause the product to miss an important launch window.

What should the project manager do?

A.

Escalate the issue to the project sponsor that legal requirements were not provided during planning.

B.

Create the product and release without legal review to meet the scheduled timeframe.

C.

Engage an external legal company to validate in-house legal review.

D.

Request a cost-benefit analysis of launching to market considering the legal review addition.

At the beginning of a project, a project manager forms development teams comprised of internal and external team members. Some of these team members possess

diverse experience and seniority, The project manager knows that the project work will include challenging tasks and require expert skills.

What should the project manager do?

A.

Ask the functional manager to replace inexperienced resources with qualified ones.

B.

Organize the teams based on customized levels of expertise to leverage the activities.

C.

Create a team with the highest expertise and seniority for complex project activities.

D.

Ask the learning department to initiate a skill-level program for those inexperienced resources.

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.

During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.

Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.

How should the project manager address the administrative staff’s data security concerns related to project scope implementation?

(Refer to the Health Records Modernization at Hospital Case Study exhibit.)

A.

Proceed with implementation and address their security issues as part of the scope.

B.

Engage the IT department to address the security issues.

C.

Include them in security planning sessions and demonstrate the security measures.

D.

Minimize system security to speed up the implementation.

A project manager is identifying stakeholders for a research project. The stakeholders that are included are individuals from academia, industry, and government.

What should the project manager do once stakeholders are identified?

A.

Communicate with the stakeholders about the progress of the project on a regular basis.

B.

Conduct facilitation sessions with the stakeholders to understand and align their expectations.

C.

Focus on key stakeholders who are critical to the project.

D.

Engage the stakeholders based on their influence on the project.

A project manager is leading a software development project. During the second sprint, there is a change in the company ' s artificial intelligence (Al) policy that now

permits using the organization ' s proprietary generative Al model, which the software development team can use to increase coding efficiency.

What should the project manager do first?

A.

Arrange for the needed training before implementing the change.

B.

Trigger the change management process for immediate actions.

C.

Assess the impact of the change to understand the risks involved.

D.

Meet with the stakeholders to get their consensus about the change.

A business stakeholder is unhappy that the team is using a predictive artificial intelligence (AI) model for cash-flow planning. However, the tool has been very effective and has prevented funding challenges.

How should the project manager address the stakeholder’s concerns?

A.

Share the merits of the tool with the stakeholder and continue using it.

B.

Present the successful results to the project sponsor and continue using the tool.

C.

Brief the team on the stakeholder’s dissatisfaction and proceed with the tool.

D.

Temporarily stop using the tool and convince the stakeholder before continuing.

A project manager is completing a project that required machinery from several different vendors. Similar projects in the future may require the project manager to use

the same vendors again; however, the quality and performance of the vendor products varied, creating project risk.

What should the project manager do to facilitate the success of future projects?

A.

Negotiate future prices with the vendors while there is still a positive relationship.

B.

Document the vendors ' performance regarding quality and delivery time internally.

C.

Update the vendor database and ensure key vendor contact information is current.

D.

Notify the underperforming vendors that better pricing and quality will be expected in the future.

Page: 3 / 3
Total 187 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved