Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 11
Total 2040 questions

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

A.

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

A.

Update the restriction log with the new team capacity.

B.

Explain the new project requirements to the team.

C.

Update the project budget with the released team members.

D.

Explain the new team velocity to the customer.

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Consult with the project management office (PMO) for guidance on project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference.

D.

Document the project sponsor's instructions as the archived project artifacts.

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

A.

Report the violation to the change control board (CCB) and seek comprehensiveapproval for these modifications.

B.

Update the change management plan to define the level of control required forthese types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no actionbecause the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

A.

Evaluate the engagement needs of stakeholders.

B.

Distribute weekly status emails to stakeholders.

C.

Engage the sponsor on the behavior of stakeholders.

D.

Conduct weekly update meetings with stakeholders.

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member's tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

A.

Assess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?

A.

Create a scope baseline and put the rest as backlog activities.

B.

Estimate the work the team can complete and define story sizes to keep the project under control.

C.

Develop a plan to complete more work In less time.

D.

Spend a short amount of time defining the scope and building prototypes to refine the requirements.

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

A.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

B.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer

C.

Ask the customer to simplify the feature so that it can be implemented in one iteration

D.

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Page: 2 / 11
Total 2040 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved