PMP PMI Project Management Professional (PMP) July 2026 Update Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI PMP Project Management Professional (PMP) July 2026 Update certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
A project manager joined an ongoing project to replace another manager. After one iteration, the project manager noticed that team morale is low. Team members are
reluctant to speak at first, but tell the new project manager about a history of conflicts.
What should the project manager do next?
During a review session, the team reports that the daily coordination meetings have been unproductive. The team asks the scrum master to implement a standard
format for the daily coordination meetings.
What should the scrum master do?
During the execution of an agile project, the quality of one vendor ' s deliverables decreases significantly. After analyzing possible solutions, the project manager identifies an alternative vendor who can deliver similar components in smaller batches.
What should the project manager do?
A strategic project is nearing completion. The project manager discovers the project team is reluctant to prepare the knowledge transfer documentation to the relevant business department because they are being assigned to a new, urgent project.
What should the project manager do?
A project manager is leading an important development project. A key deliverable has been completed but does not meet the quality standards defined in the quality management plan.
What should the project manager do?
A project manager is working for a multinational financial services company that does business in more than 100 countries. The company is rolling out a time
management system in multiple countries.
What should the project manager do?
A project sponsor provides a charter and appoints a project manager to implement a large project over 5 years. The sponsor then requests the project budget and
outcomes from the project manager.
What should the project manager do first?
Midway through a product launch, a major supplier announces a three-week shutdown due to a warehouse fire. This supplier provides hardware that is critical to integration testing.
What should the project manager do?
One of the key team members working on a critical path task resigns without any notice. Another resource is hired as a temporary replacement but does not have the same skillset and is taking too long to complete the work.
What should the project manager do?
A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project ' s activities.
According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists
the project should move forward because customers will be impacted if the equipment is not available.
What should the project manager do?
A project manager works for a company that recently won a big government contract. The company has a flat hierarchy and self-organized teams. The client wants
the project manager to use a predictive management approach and an up-front project management plan. However, the project manager knows that a more agile
approach would be better due to the high uncertainty of the project scope.
What should the project manager do?
The project manager is creating a status report to show the progress of completed training artifacts intended for delivery to bank branches for a new project for both
new and existing customers. During the review process, it is discovered that some of the artifacts were duplicated by two project team members.
What should the project manager do?
Aclient in a consulting firm presents an aggressive product implementation schedule. Key aspects of the scope have not been defined, and several internal
stakeholder decisions are still pending. This situation is delaying the request for proposals (RFPs) from the vendors.
What should the project manager do?
A project manager notices that every time a new member joins the team, they spend too much time learning business terminology. This trend has impacted system
integrations and creates delays on a few tasks that other teams depend on.
What should the project manager do?

According to the Alpha project’s risk management report, which risks should the project manager prioritize?
(Refer to Alpha Project — Risk Management Report exhibit.)
During the planning phase of a project, the local project team presents a task to the project manager. This task will require several months to complete, and the
duration will affect the expected timeline.
What should the project manager do first?
During a sprint review, the customer described a strong market trend that will highly impact the product vision and the project management plan. What should the
project manager do?
During a daily coordination meeting, the team reports that due to considerable challenges with the infrastructure, the planned tasks are now blocked and cannot move
forward. What should the project manager do?
At the postevent review of an annual conference, the project manager realizes that the team could benefit from improvements in how they handle sponsorship
agreements and event logistics. Specifically, the team found that having clearer contracts with sponsors earlier in the planning process would help avoid last-minute
issues.
How should the project manager handle the organizational process assets (OPAs)?
Acompany is transitioning all projects under the portfolio of IT from a predictive to an adaptive approach. Some of the project managers and project team members
are unhappy about this change because they have been working in a predictive environment for years, and several projects are currently in progress.
What are two tasks the project manager should ask support from the company ' s management team to ensure smooth transition to the new approach? (Choose 2)