Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 9
Total 1704 questions

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

A.

Mitigate the risks that are applicable to the current and following iterations.

B.

Focus on the project deliverables rather than the documented risks.

C.

Agree that any issue can be handled when it becomes a problem.

D.

Acknowledge that the risks will be handled in the corresponding iteration.

During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project

manager ensure the team is fully productive?

A.

Review the project backlog during the team's standup meeting.

B.

Encourage project team members to prioritize the product backlog.

C.

Ensure team members are working according to the project plan.

D.

Work with the product owner to ensure the project backlog is prioritized.

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

A.

Review the risk register and assign functional managers as resources.

B.

Analyze the resource pool and assign internal resources who participated in past projects.

C.

Perform an analysis of the key cost drivers and present alternatives.

D.

Review the work breakdown structure (WBS) to ensure there are adequate resources.

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project

manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?

A.

Advise the team member not to share personal information from past projects with the entire team.

B.

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

C.

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

D.

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

A.

Establish a probability and impact matrix and plan response criteria.

B.

Disregard the situation since it is not hindering the project deliverables.

C.

Develop a joint policy among the various organizations.

D.

Escalate the issue to the project sponsor and seek their guidance.

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

A.

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.

Reschedule the kick-off meeting for the following month so all can attend on-site.

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

A.

Modify the project schedule to accommodate the delays in the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.

What should the project manager do next?

A.

Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed.

B.

Start the project and deal with these budget issues as they arise throughout the project life cycle.

C.

Add the missing budget items to the risk log and present them in the next project steering committee.

D.

Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy.

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.

What should the project manager do?

A.

Use the compliance issues to identify coaching and mentoring opportunities.

B.

Log the feedback from the compliance gaps in the lessons learned register.

C.

Review this with the project sponsor to avoid compliance gaps and issues.

D.

Discuss the suggestions with the staff responsible for the compliance issues.

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are

likely to require this knowledge in the future.

What should the agile project manager do?

A.

Ask the team member to develop more expertise and become a subject matter expert (SME).

B.

Ask the team member to provide a training session for the rest of the team.

C.

Ask the team member to produce a lessons learned document and share it with the team.

D.

Ask the team member to record highlights the team may want to know.

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

A.

Detail the reason for the project delay in the status report.

B.

Invite the stakeholders to discuss a mitigation plan.

C.

Take on some of the necessary work to minimize the impact.

D.

Register an issue and escalate it to the project sponsor.

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

A.

Identified the vice president as a stakeholder

B.

Recorded the vice president's concerns in the risk register

C.

Escalated any dissent to top management right away

D.

Shared project boundaries so that everyone was aware of the scope

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has

too many items to allow on-time delivery.

What should the project manager do first?

A.

Update the risk register and present a contingency plan to meet the deadline.

B.

Suggest to the customer to reduce the backlog to meet the date.

C.

Increase the capacity of the team to finish the project on time.

D.

Ask the team to propose a minimum viable product (MVP) to meet the date.

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

A.

Informal written communication, such as a friendly reminder

B.

Formal written communication, such as an email with a copy sent to the manager

C.

Informal verbal communication, such as a conversation

D.

Formal verbal communication, such as a conversation at the end of the sprint retrospective

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

A.

Lessons learned database

B.

Procurement strategy

C.

Vendor's website

D.

Appropriate financial regulations

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?

A.

Reschedule the project until the local travel restrictions are lifted.

B.

Schedule virtual sessions with the specialist to guide the team in completing the activity.

C.

Seek additional budget to train the project team on the required skill set.

D.

Refer to the organization's lessons learned repository and find an alternative solution.

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

A.

Explain to the team that open discussions are needed but remind the team to follow the ground rules.

B.

Ask this member to only discuss the current topic to achieve team efficiency.

C.

Ask the team to accept the input from this particular member as their input may be useful.

D.

Allow the self-organized team to discuss the situation among themselves and come to a resolution.

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.

B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.

C.

Contact the project sponsor to let them know you require more resources to meet the schedule.

D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.

A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.

What should the project manager do?

A.

Assign an experienced team member to work with this member on a daily basis in order to become knowledgeable about the technology.

B.

Arrange formal training for this member to gain sufficient knowledge to reduce the impact on team performance.

C.

Let this team member understand the urgency and encourage them to spend extra time to become knowledgeable about the technology.

D.

Let the team lead the meeting discussions so that every member has a chance to prepare and speak up.

A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an

approval from the design department will be needed.

What should the project manager do?

A.

Meet with the design manager to ask for the necessary approval.

B.

Invite a design team member to the next daily meeting.

C.

Update the issue log and escalate it to the project sponsor.

D.

Replace this iteration deliverable for one without any blockers.

An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have

agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.

Which approach should be used in this situation?

A.

A flow-based approach starting with the smallest stories.

B.

An iterative approach starting with the highest value epic.

C.

A predictive approach with short phases.

D.

An incremental approach with a minimum viable product (MVP).

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project

manager use to manage these risks using an agile approach?

A.

Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.

B.

Implement a scrum risk retrospective to analyze the risks at the end of the project.

C.

Assign an agile risk manager to better understand and track the project risks.

D.

Evaluate the risks constantly and reprioritize work as the project progresses.

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

A.

Discuss with the team how the project objectives can be met.

B.

Request that the sponsor increase the bonus for high performers.

C.

Schedule a team-building activity to boost the team's morale.

D.

Organize a team meeting to remind the team of the ground rules.

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?

A.

The project sponsor should select the project artifacts that the project manager and project management team should use in the project.

B.

The project manager and project management team should use the standard project artifacts from the database.

C.

The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.

D.

The project manager and the project management team should select the appropriate artifacts for use in the specific project.

A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?

A.

Estimate the backlog items to forecast quality.

B.

Ask the senior manager to approve the user acceptance testing (UAT) plan.

C.

Review the quality management plan with the senior manager.

D.

Inform the senior manager that there are approved quality standards.

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV)

to actual cost (AC) for the project and has found the calculated result to be 0.9024.

What does this value mean for the project?

A.

The project has started exceeding the planned cost.

B.

The project is earning less value an was planned.

C.

The project has earned more value than planned.

D.

The project is close to exceeding the planned cost.

During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to

be involved in the regular project communications and reporting cycles.

What should the project manager do?

A.

Ask the project team members to include the manager in all of their communications regarding this project.

B.

Inform the manager that only stakeholders identified in the communications management plan should be involved.

C.

Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

D.

Suggest the manager contact the steering committee and project management office (PMO) to be included.

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.

What should the project manager do?

A.

Ensure that people care about each other and work effectively together through effective team management.

B.

Meet with the team to discuss the correct, expected behavior in stressful situations and start practicing it.

C.

Establish a productive environment where all team members can assist one another with the workload.

D.

Create an environment of respect and fairness so the team can increase their project performance in stressful situations.

The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.

What should the project manager do?

A.

Help engineer A to become familiar with this new role and ensure engineer B stays motivated.

B.

Promote engineer B instead since the project manager has the authority to make this decision.

C.

Request management approval that engineer B will be promoted if engineer A fails in this role.

D.

Coach engineer B to be prepared to perform this role if and when engineer A fails.

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Match the following common terms with their explanations that evaluate the buffers or constraints.

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

A.

Delegate most authorities and control the authority by withholding important information.

B.

Delegate certain authorities and control the authority by withholding important information.

C.

Delegate certain authorities and share information to allow fair decision-making.

D.

Delegate most authorities and share information to allow fair decision-making.

A project manager is part of a balanced matrix project organization. The project manager will receive all work performance updates directly from the new sourcing

department head who has no time to spare to give the project manager the information.

What should the project manager do?

A.

Request information directly from the sourcing department team members.

B.

Present the situation to the manager of the sourcing department head.

C.

Discuss the situation with the company project sponsor for advice.

D.

Work out a resolution in consultation with the sourcing department head.

A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?

A.

Discuss ground rules with the team that will include daily meetings.

B.

Use one-to-one virtual meetings because they are more efficient.

C.

Ask senior management for coaching regarding this situation.

D.

Agree on a new time and reschedule the daily standups.

During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?

A.

Replace the team member with another available resource on the team.

B.

Discuss the situation with the team member's functional manager to see if the schedule can be adjusted.

C.

Check with the project management office (PMO) on the available resources to complete the activities.

D.

Encourage the team member to prioritize scheduled project activities.

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

A.

Review the cost and schedule baselines for execution.

B.

Define change management for the new technology.

C.

Analyze the cost and identify the project benefits.

D.

Identify the risks in implementing the new technology.

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites,

the office, and remote locations. In addition, some team members have limited access to the electronically shared files.

How should the project manager manage this challenge?

A.

Request changes in the processes since it is not suitable for the company environment.

B.

Communicate a strong message to the team explaining the importance of knowledge transfer.

C.

Study the environment and the available resources to determine which approach to use.

D.

Send the intended information through email since it is the primary communication tool.

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

E.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Inform the project sponsor of the stakeholder's dissatisfaction.

C.

Document the issue in the issue log and send a report to management.

D.

Review the requirements traceability matrix and conduct inspections.

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.

What should the project manager do first?

A.

Increase the capacity of the team to finish the project on time.

B.

Update the risk register and present a contingency plan to meet the deadline.

C.

Ask the team to propose a minimum viable product (MVP) to meet the date.

D.

Suggest to the customer to reduce the backlog to meet the date.

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

A.

Register a new risk in the risk management plan.

B.

Ask for additional resources and review the project estimate.

C.

Review organizational process assets (OPAs) and perform analogous estimating.

D.

Complete a bottom-up estimation for the project activities.

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

A.

Consult the risk response plan.

B.

Assign the tasks to another team member.

C.

Update the resource calendar.

D.

Issue a request to the change control board (CCB).

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.

Which approach should the project manager use as a servant leader?

A.

Ask stakeholders to find and self-fund education about this new technology.

B.

Allocate resources to provide training about the new technology to the stakeholders.

C.

Contact the project sponsor to get those stakeholders removed from the project.

D.

Escalate the issue with upper management to find a novel solution for this situation.

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

A project manager discovers that the project team is spending a large amount of time delivering several reporting formats for the same project updates to multiple stakeholders. What should the project manager do to reduce the time spent on these activities?

A.

Segment the types of communications to be delivered to different stakeholders.

B.

Update the communications management plan to remove less influential stakeholders.

C.

Hold biweekly status meetings to deliver information to all stakeholders at once.

D.

Delegate all of the stakeholder communications activities to a project team member.

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Page: 5 / 9
Total 1704 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved