Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 10
Total 1988 questions

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reaction

time.

C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

A.

Escalate the obstacle to a servant leader for resolution.

B.

Ignore the obstacle and present the partial solution to the customer

C.

Focus on generating business value despite the obstacle

D.

Make changes to reprioritize the backlog because of the obstacle.

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.

B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex

items.

C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define

the project scope.

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

A.

Communicate with the industry's regulatory authority to grant the company an exception

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Comply with the regulatory requirements and work to compress the project schedule.

D.

Hire a third party who is an expert on the industry's regulations to work out the details.

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?

A.

Inform the team not to accept any changes, as it involves significant rework.

B.

Request management to update the project requirements accordingly.

C.

Request an update of only new requirements, as other changes involve rework.

D.

Inform management that the agreed-upon scope cannot be changed.

A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.

What should the project manager do to keep the team performing as effectively as possible?

A.

Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,

B.

Transition the team from an agile approach to a predictive approach for better performance cantral.

C.

Provide the team with virtual collaboration software and training on the software to minimize disruption,

D.

Evaluate project performance and step in if performance decreases to. an unacceptable level,

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

A.

Ensure the change management plan highlights this requirement to prevent future issues.

B.

Update the project charter with this information regarding change management.

C.

Update the project risk register to identify this risk and describe how to mitigate the issue.

D.

Talk with the client to ensure they are aware of the change management procedure.

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

A.

Increase the contingency reserves to cover unknown-unknowns.

B.

Implement short cycles for inspection and provide feedback.

C.

Increase the management reserves to convert the known-unknowns.

D.

Create a new risk entry to identify the stakeholder as a detractor.

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A.

30/40

B.

40/70

C.

30/70

D.

40/30

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

A.

Reassess the risk log to ensure it is up to date.

B.

Monitor quality metrics to ensure the project continues as planned.

C.

Perform lessons learned to ensure the issue does not happen again.

D.

Schedule a team meeting to review the issue,

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.

In the initiation process, as it happens concurrently with the project contract and project charter creation

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

A.

Ask the project sponsor to replace the contractor since they do not have agile experience

B.

Issue a formal notice to the contractor to obtain an agile certification

C.

Consult the project team to understand the extent of the training needs for the contractor

D.

Instruct the contractor to receive agile training since the project has already started

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

A.

Let the project team pull the recommended work from the bottom of the backlog to

maximize value creation.

B.

Analyze and reprioritize the backlog and provide the decision to the product owner

and team.

C.

Recommend the product owner prioritize the missing work higher because it is

needed for the minimum viable product (MVP).

D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

A.

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager

schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?

A.

Accommodator

B.

Mediator

C.

Arbitrator

D.

Conciliator

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Page: 5 / 10
Total 1988 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved