Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 11
Total 2040 questions

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.

B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.

C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.

D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.

A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?

A.

Follow a predictive approach in order to obtain formal acceptance of each deliverable

B.

Work with the product owner to define the minimum viable product(s)

C.

Reinforce the negotiation and soft skills of the team through training

D.

Develop and monitor a plan with due dates to reduce the time of completing the product

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?

A.

Persuade this stakeholder using emotional intelligence skills to obtain acceptance.

B.

Obtain final acceptance from another stakeholder who is also familiar with the project

C.

Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.

D.

Create a project acceptance waiver noting the stakeholder’s concerns so they can be addressed later

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?

A.

Defined the expected agile team contribution in the creation of the backlog.

B.

Assessed the capabilities of the agile team and planned for the required training

C.

Defined the team ground rules and shared project vision.

D.

Communicated project vision and sprint goals clearly to the team

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

A.

Determine which agile software tools will be required to support agile delivery within the organization

B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.

Determine how to transform the organization using agile techniques, including organizational training and communications

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

A.

Networking

B.

Emotional intelligence

C.

Conflict management

D.

Influencing

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have differentstakeholders than the previous project

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

A.

Coach those team members lacking hybrid knowledge to learn on the job.

B.

Change the team to include hybrid experts

C.

Assess the required training per team member.

D.

Deliver hybrid training to all team members

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

A.

Schedule a steering committee meeting and obtain their approval on the request

B.

Support the decisions of the team and transfer the decision making responsibility to them.

C.

Inform the team that although this is a hybrid environment, the project managermust still be responsible for making decisions

D.

Consult the product owner about letting the resources make decisions

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?

A.

Request that the customer reviews and clarifies feature definitions for the current sprint

B.

Send a burndown chart of the current sprint to the customer and seek clarifications.

C.

Educate the customer and have them participate in daily standup meetings.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

A.

Request direction from the project sponsor

B.

Write an email to the client requesting clarification

C.

Seek support from the development manager.

D.

Work with the product owner to clarify the requirement

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

A.

Address the lack of performance by coaching the new team member

B.

Discuss options to improve performance with the resource manager

C.

Provide performance feedback as part of the retrospective ceremony.

D.

Request a more efficient replacement resource from the project sponsor

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?

A.

Update the issue log and act to minimize the impact

B.

Update the schedule to include the delay

C.

Add the risk and the delay to the risk register

D.

Escalate to the management team for delay approval

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase

B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

C.

Consult with experts on methods to reduce costs and increase the financial value of the project

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

The project schedule is falling behind and the project manager observes that the project team seems to be spending the majority of their time writing documentation instead of performing project tasks What should the project manager do to help ensure that the team focuses on project tasks?

A.

Assign a team member to handle the documentation activities.

B.

Coach the project team to complete the project documentation activities

C.

Review and adapt the appropriate project artifacts.

D.

Save all documentation activities until tire end of the project

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?

A.

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.

B.

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly

C.

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making

D.

Review the adequacy of the project's governance and ensure that an appropriate structure is in place

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project

What should the project manager do first to determine a governance approach for the project?

A.

Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project

B.

Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines

C.

Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines

D.

Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

A.

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.

Conduct a project scope review workshop with relevant stakeholders.

D.

Conduct project planning meetings in one location with relevant stakeholders

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

A.

Share this opportunity with another project

B.

Establish a contingency reserve to support the opportunity

C.

Further monitor the opportunity

D.

No more action is required

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

A.

Set up a training session for all project team members

B.

Reach out to the functional managers for support

C.

Speak individually with each project team member about making the needed updates

D.

Send an email asking all project team members to complete updates at the end of the day

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

A.

Hire a team of external users to perform acceptance testing on the product.

B.

Define a user focus group as external stakeholders with a high influence on outcomes

C.

Hire a consultant to perform a benefit analysis as an input to the project charter.

D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?

A.

Train the team on the new regulations as requested by management

B.

Get commitment from the team to include all of the required regulations

C.

Ask the project sponsor to add more time to the project.

D.

Share with participants the need to focus only on product functionality

A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials

What should the project manager do next?

A.

Ask the project sponsor to allocate more budget to cover the costs

B.

Update the procurement management plan and negotiate with the contractor.

C.

Ask the contractor to review the offer and reduce the costs.

D.

Update the procurement strategy and negotiate with the contractor

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery

Page: 5 / 11
Total 2040 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved