Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 6 / 6
Total 594 questions

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

A.

Set up a meeting with the product owner to discuss the stakeholder's concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder's concern in the issue log.

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

A.

Recurrent team meetings are planned to control the budget against future uncertainties.

B.

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.

The budget was developed by using the lessons learned from previous project data.

D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.

How can the project manager address this challenge to assure outsourced vendors deliver?

A.

Review the coordination and communication costs with the supplier.

B.

Develop a new strategy for communication and management of resources.

C.

Review the risk management plan for the mitigation activities.

D.

Submit a change request to increase the contingency budget.

The project manager of a globally dispersed team evaluates the organization's current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings.

Which action should the project manager take to improve remote engagement?

A.

Implement a new suite of collaboration tools to provide various communication options for the team.

B.

Organize an in-person, team-building event to improve team engagement and communication.

C.

Schedule one-on-one meetings with the team members to understand their specific needs and challenges.

D.

Survey all team members to identify common issues with virtual engagement and address them systematically.

A project team working on a big data project has concluded the make-or-buy decision on a particular feature, which will drive an increase in product adoption. The team decided to buy commercial software.

What should the project manager do next?

A.

Request a purchase order.

B.

Inform the project sponsor.

C.

Update the risk register.

D.

Finalize change control.

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

A.

Have the team complete the technically complex story first.

B.

Work with the product owner to clarify and prioritize the backlog stories.

C.

Have the team complete the less complex story first.

D.

Work with the agile coach on the user stories to avoid conflict.

A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.

How should the project manager improve the team's understanding?

A.

Involve team members in stakeholder analysis and engagement.

B.

Invite all stakeholders to progress meetings to avoid ambiguity.

C.

Ensure team members have access to a well-written requirements traceability matrix.

D.

Engage with the project sponsor and ensure the product backlog is correct and up to date.

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.

Update the schedule and project risk register according to the regulatory requirement.

C.

Consult the project management plan for guidance on addressing the regulatory requirement.

D.

Assess the impact of implementing the potential regulatory requirement on the project.

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

A.

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.

B.

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.

C.

Submit a request for extra time and budget related to the dependencies and technical difficulties.

D.

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

Drag the items on left side to the matching term within the correct project approach on the right side.

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?

A.

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.

B.

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.

C.

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.

D.

Explain that each individual newsletter is based on specific categories of communication for the intended audience.

A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users.

What should the project manager do?

A.

Ensure that the user guide is detailed and has clear instructions.

B.

Ensure that comprehensive documentation is handed over.

C.

Ask the project team to provide operational support for 1 year.

D.

Ensure that knowledge is transferred to the operations team.

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

A.

Contact the human resources (HR) department to find new resources to replace this critical resource.

B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.

C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.

D.

Discuss the resource management plan with the project team for effective utilization of critical resources.

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Drag the communication event on the left to the main subject discussed during the event on the right.

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

A.

Review the conformity management plan to ensure the requirements are clearly defined.

B.

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.

Evaluate industry standards of similar products to determine which apply to this project.

E.

Ask the suppliers to create a statement of conformity when the product is delivered.

A scrum master noticed that one of the team members is afraid to ask questions, does not like to collaborate with other team members, and avoids taking responsibility for their actions. What is the likely reason that would cause a team member to behave that way?

A.

Lack of technical skills

B.

Fear of conflict

C.

Lack of experience

D.

Company culture

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

A.

Assessed feasibility and impacts

B.

Developed benchmarking

C.

Analyzed stakeholders

D.

Detailed the project charter

A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.

What should the project manager do first?

A.

Assess and analyze the impact of using these metrics.

B.

Involve the team in reviewing the proposed metrics.

C.

Request an extension to implement the new metrics.

D.

Support the required metrics during the next project phase.

A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.

Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)

A.

Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.

B.

Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.

C.

Assess the gaps and assign an expert resource for respective areas of knowledge.

D.

Identify external subject matter experts (SMEs) and plan training sessions to conduct knowledge transfer.

E.

Schedule shadowing sessions among team members to facilitate team learning.

A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?

A.

Ask the project team to meet and document why the stakeholder's approach is incorrect.

B.

Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.

C.

Discuss the issue with the project team during a project status meeting and request that they change the approach.

D.

Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.

A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.

What should the project manager do?

A.

Support the suppliers by providing them with additional resources.

B.

Execute the risk response plan and update the issue log.

C.

Ask suppliers to submit a revised plan and schedule.

D.

Execute the risk response plan and update the action register.

A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

A.

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.

As the project sponsor has requested a detailed time line up front, an agile approach is the best option.

C.

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

Page: 6 / 6
Total 594 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved