Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PgMP PMI Program Management Professional (PgMP) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PgMP Program Management Professional (PgMP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 7
Total 452 questions

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

A.

Accept the assignment, identify the skill gaps, and request training.

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified.

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager.

D.

Reject the assignment because of fear of failure and resulting negative career impact.

You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

A.

Contract administration

B.

Resource management

C.

Resource control

D.

Procurement management

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.

What should the program manager do next?

A.

Reassess the project manager’s credentials

B.

Assign a different project manager

C.

Review the skill requirements of the project

D.

Apply the competence assessment techniques to resolve the issue

You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?

A.

Project management plan

B.

Organizational process assets

C.

Project deliverables

D.

Quality control measurements

Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

A.

Change register

B.

Integrated change control

C.

Program Management Information System

D.

Change log

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

A.

.83

B.

-$20,000 C. .91

C.

Negative ten percent

In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

A.

Program governance

B.

Organizational process assets

C.

Program standards

D.

Process analysis

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha’s program closure plan?

A.

Execute the transition plan, and include knowledge transfer to transition Alpha support to operations.

B.

Keep the Alpha program open until support is no longer required, then execute program closure.

C.

Adjust Alpha’s exit criteria to ensure its support is included in the Beta program.

D.

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta.

A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.

What is the other part of the review?

A.

Tracking and reporting on benefits management plan

B.

Identifying factors influencing delivery of benefits

C.

Demonstrating that other stage gate requirements have been met

D.

Gathering additional stakeholders' requirements

An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?

A.

$1,158,250

B.

It depends on the internal decision making process. C. $2,074,249

C.

$1,550,000

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

A.

Select the best bid from the prequalified vendor list.

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid.

D.

Add the new vendor to the prequalified list and replace the project manager.

Which of the following is described in the statement given below?

"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."

A.

Stakeholder register

B.

Program scope statement

C.

Governance plan

D.

Organizational chart

Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

A.

Alternative identification

B.

Work packages

C.

Requirements

D.

Scope decomposition

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.

Which of the following actions should the program manager take?

A.

Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.

B.

Balance stakeholder needs through the use of trade-offs among the stakeholder groups.

C.

Focus on the external stakeholders to ensure the intended benefits are achieved.

D.

Conduct a stakeholder meeting to allow everyone to state their priorities.

A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.

Before initiating closeout and releasing the resources, what should the program manager do?

A.

Review the benefits management plan with the program sponsor

B.

Obtain approval from the sponsor to close the program

C.

Prepare performance evaluations for all program personnel

D.

Prepare performance evaluations for all project personnel

A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address QUESTION NO:s. The new country manager used this social media platform at a previous job.

What should the regional program manager do to address the country manager’s request?

A.

Suggest that the country manager use the existing communication channels while the team becomes familiar with the new social media platform.

B.

Ask the country manager to champion the social media platform, as they may have more influence than the regional program manager.

C.

Review existing in-house social media capabilities to determine if they will meet the needs of the country manager’s request, and update the stakeholder register.

D.

Ask the technology, security, and project teams to assess the country manager’s request.

You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

A.

Project charter

B.

Project scope statement

C.

Project resource requirements document

D.

Roles and responsibilities chart

Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations. They claim that their

department did not approve this service, and is now unprepared and untrained to support the transformation. What should the program manager have done first to prevent this?

A.

Added the operations manager as a key stakeholder

B.

Created a transition plan during the planning phase for the impacted operational area

C.

Ensured there was a communications management plan that included the transition to operations

D.

Drafted a training plan with assistance from the program management office (PMO) or human resource department before transitioning it to operations

Page: 1 / 7
Total 452 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved