Prepare effectively for your PeopleCert MSP-Practitioner MSP Practitioner, 5th edition Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 2
Total 133 questions

Which of the following is an influencer type of stakeholder?

A.

Management board

B.

Business partner

C.

Media

D.

Supplier

Which of below sentences describes Project Brief?

A.

List of all projects that will be part of programme

B.

Control framework for programme

C.

Control framework for projects

D.

Describes purpose, cost, time, performance requirements and constraints of a project

As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?

A.

Keep informed, active consultation, maintain interest

B.

Active consultation, keep informed, maintain interest

C.

Keep informed, maintain interest, active consultation

D.

Maintain interest, active consultation, keep informed

The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers.

Is this an appropriate application of the ‘identify the programme' process, and why?

A.

Yes, because time should not be wasted creating detailed costs and budgets during the identify the programme’ process

B.

Yes, because the programme manager needs to have some understanding of the cost before agreeing to proceed (or close)

C.

No, because a detailed financial plan will be developed to understand the costs during the ‘plan progressive delivery’ process

D.

No, because the previous roll-out of smart metering services was for electricity and gas, not water, and the costs will be different

Programme needs to create a working environment that is both robust and flexible enough to be able to cope with frequent and sometimes radical changes of boundary. Which programme management principle suggests this?

A.

Leading change

B.

Remaining aligned with corporate strategy

C.

Envisioning and communicating better future

D.

Adding value

POTI model is part of which governance theme?

A.

Business Case

B.

Blueprint

C.

Vision

D.

Risk and issue management

Which of the following is a KEY attribute for a Programme Manager?

A.

Have ongoing operational responsibilities within their business area

B.

Change management skills

C.

A good knowledge of project management approaches

D.

Have access to key stakeholders

Which of the following is not correct about 'Leading change'?

A.

Appoint right people at right time

B.

Actively engage stakeholder

C.

Create novel solutions to problems

D.

Get approval from sponsoring group

Which of following is not a principal control for managing the tranches?

A.

Business Case

B.

Benefit Review

C.

Business Case

D.

Dependency management

Which of the following statements best defines 'transformational Flow'?

A.

Common factors of success derived from lessons learned in programmes that had both positive and negative results

B.

Allow organizations to put in place right leadership, delivery team, robust organization structures and controls

C.

Provides a route through lifecycle of a programme, from its conception through to delivering new capability

D.

Temporary flexible organization created to coordinate, direct and oversee implementation of set of related projects

Which of the following statements best defines 'MSP Principles'?

A.

Common factors of success derived from lessons learned in programmes that had both positive and negative results

B.

Allow organizations to put in place right leadership, delivery team, robust organization structures and controls

C.

Provides a route through lifecycle of a from its conception through to delivering new capability

D.

Temporary flexible organization created to coordinate, direct and oversee implementation of set of related projects

Which of following is part of critical benefits validation test?

A.

Currency

B.

Accurate

C.

Attribution

D.

Availability

Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

Which of the following is Not one of MSP defined levels of stakeholder engagement?

A.

Maintain Interest

B.

Formally Approve

C.

Active Consultation

D.

Keep informed

Who is accountable for confirming programme closure?

A.

SRO

B.

Programme Manager

C.

Sponsoring group

D.

BCM

Which individual is MOST LIKELY to be appointed as the SRO?

A.

Chief Finance Officer

B.

Human Resources Director

C.

Chief Technology Officer

D.

Chief Engineering Officer

Which of the following statements is NOT TRUE?

A.

The SRO is accountable for confirming Programme Mandate.

B.

The SRO is accountable for the Programme Brief.

C.

The Programme Manager is responsible for the Vision Statement.

D.

The Programme Manager is responsible for the Blueprint.

The programme is in the ‘plan progressive delivery' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.

During which activity is the SRO responsible for providing formal approval for this recommendation?

A.

Continue to develop and validate programme plans

B.

Confirm business case

C.

Prepare for the next process

D.

Agree to proceed (or close)

In which MSP theme would you expect to find the POTI model?

A.

Vision

B.

Blueprint Design and Delivery

C.

Leadership and Stakeholder Engagement

D.

Planning and Control

The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.

Is this an appropriate application of the ‘plan progressive delivery' process, and why?

A.

Yes, because the Call Centre Manager should commit the resources before Tranche 1 begins

B.

Yes, because resources from the call centres will be critical to the success of Tranche 1

C.

No, because the sponsoring group should commit the resources before Tranche 1 begins

D.

No, because resources should be appointed by the project management team when Tranche 1 begins