MSP-Practitioner PeopleCert MSP Practitioner, 5th edition Exam Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PeopleCert MSP-Practitioner MSP Practitioner, 5th edition Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which of the following is an influencer type of stakeholder?
Which of below sentences describes Project Brief?
As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?
The programme manager has produced a rough estimate of costs based on the recently completed roll-out of smart metered services to electricity and gas customers.
Is this an appropriate application of the ‘identify the programme' process, and why?
Programme needs to create a working environment that is both robust and flexible enough to be able to cope with frequent and sometimes radical changes of boundary. Which programme management principle suggests this?
POTI model is part of which governance theme?
Which of the following is a KEY attribute for a Programme Manager?
Which of the following is not correct about 'Leading change'?
Which of following is not a principal control for managing the tranches?
Which of the following statements best defines 'transformational Flow'?
Which of the following statements best defines 'MSP Principles'?
Which of following is part of critical benefits validation test?
Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

Which of the following is Not one of MSP defined levels of stakeholder engagement?
Who is accountable for confirming programme closure?
Which individual is MOST LIKELY to be appointed as the SRO?
Which of the following statements is NOT TRUE?
The programme is in the ‘plan progressive delivery' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.
During which activity is the SRO responsible for providing formal approval for this recommendation?
In which MSP theme would you expect to find the POTI model?
The programme is in the ‘plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the ‘plan progressive delivery' process, and why?
