Prepare effectively for your USGBC LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 6
Total 337 questions

Which of the following statements are true for Erosion and Sedimentation Control (ESC) plan prerequisite compliance?

A.

The ESC plan cannot be modified during the design phase of the LEED certification

B.

The ESC plan can be developed or modified during the design phase of LEED certification

C.

A compliant ESC plan may be developed during construction

D.

A compliant ESC plan must be in place when the commissioning authority is appointed

Which of the following strategies will aid in reducing indoor water use?

A.

Design drip irrigation for landscape

B.

Use high-efficiency HVAC systems

C.

Exclude janitor closets in the building

D.

Optimize consumption of showerheads

When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?

A.

Measure densities within a ¼ mile (0.40 km) radius of the project boundary

B.

Measure densities within a ¾ mile (1.20 km) radius of the project boundary

C.

Measure densities within a ⅓ mile (0.53 km) radius of the project boundary

D.

Measure densities within a ½ mile (0.80 km) radius of the project boundary

A rectangular office building is located in an extremely humid climate and is shaded by very large adjacent buildings

on all four sides. If the building owner wants to decrease the annual energy cost for operating the building, which of

the following would be the best design approach?

A.

Install glazing with a higher solar heat gain factor

B.

Install photovoltaic panels on the sides of the building

C.

Increase outdoor air intake quantities during summer months

D.

Recover waste energy through exhaust air energy recovery systems

Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:

A.

Bicycle network

B.

Emergency access

C.

Main entrance

D.

Shower room

Which of these is a method to assess the regional context of a building's design for sustainability?

A.

Conducting a site analysis

B.

Consulting with neighbors

C.

Improving a design threshold

D.

Performing an energy analysis of the building

Which of the following credits advocates the values and benefits of green building design and construction as well as outdoor physical activity?

A.

Sustainable Sites Credit, Light Pollution Reduction

B.

Sustainable Sites Credit, Open Space

C.

Environmental Quality Credit, Quality Views

D.

Location and Transportation Credit, Reduced Parking Footprint

Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

A.

A standard garbage disposal

B.

Electronic submeter at the domestic water supply pipe to the building

C.

An open-loop HVAC system that discharges potable cooling water to a nearby lake

D.

Commercial dishwasher that is ENERGY STAR® labeled or performance equivalent

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

A.

The general contractor

B.

A LEED AP

C.

The project's mechanical engineer

D.

The owner or an owner's representative

The Chartered Institute of Building Services Engineers (CIBSE) Applications Manual 10 - 2005 provides guidance for which of the following?

A.

Replacing inefficient lighting fixtures

B.

Adopting natural ventilation as the sole servicing strategy

C.

Phasing out of equipment that uses CFC-based refrigerants

D.

Renovating with materials low in volatile organic compounds

Which of the following strategies can be used to decrease the envelope load of a building?

A.

Provide summer solar shading

B.

Maximize daylighting

C.

Decrease opaque wall area

D.

Use economizers for free cooling

Which of the following is true regarding LEED Pilot Credits?

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project's scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

A project in a cold climate does not want a highly reflective roof because they want the heat absorption. How can this

project comply with Sustainable Sites Credit, Heat Island Reduction?

A.

The credit is not feasible for this project

B.

The credit may be achieved by using nonroof measures only

C.

The credit is applicable for projects that document this special condition

D.

The credit can only be achieved by using an alternative compliance path

According to the Integrative Process Credit, the discovery phase of energy-related systems should identify

A.

ventilation rates

B.

functional performance tests

C.

thermal comfort ranges

D.

transportation options

When should a preliminary water budget analysis be conducted?

A.

At the time the design development is completed

B.

At the time the plumbing contractor is selected

C.

After completion of schematic design

D.

Before completion of schematic design

What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U

A.

Coordinate open space features during the construction phase

B.

Minimize the floor-area ratio (FAR) and accessibility for open space

C.

Design a parking and road footprint layout that is not near open land

D.

Coordinate open space features early during the site planning phase

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

A.

A, B, C

B.

B, C, D

C.

C, D, E

D.

A, B, D

The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction

Practices?

A.

$10,000

B.

$12,500

C.

$22,500

D.

$25,000

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

    Energy and Atmosphere Credit, Demand Response

    Energy and Atmosphere Credit, Advanced Energy Metering

    Energy and Atmosphere Credit, Building Level Energy Metering

A.

Energy and Atmosphere Credit, Green Power and Carbon Offsets

Page: 2 / 6