PMP PMI Project Management Professional (PMBOK 7th Version) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI PMP Project Management Professional (PMBOK 7th Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team
What should the project manager do?
Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?
A project team wants to change a delivery approach for a project. Team members explain the need for a review of the information-sharing approach to ensure efficient information exchange during the project.
What should the project manager do?
A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?
Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?
A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.
What should the project lead do?
During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?
An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.
What should the project manager do?
During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.
Which approach should the scrum master use?
A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.
How should the project manager handle the situation?
A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project
manager do to finish planning?
An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
Four new teams have been formed to develop a new product. Several team members ask the project manager who will integrate the different work streams into one backlog.
What should the project manager do?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.
What should the project manager do next?
A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose 3)
An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?
The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.
What should the project manager do?
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
During a requirements review session with a customer, a team member gets upset when questioned by the customer and responds angrily.
What should the project manager do next?
A project manager has been assigned to a new project. The project manager read the business case, charter, and statement of work (SOW) and scheduled a discussion with the sponsor about the scope, goals, and objectives. The project manager requested a meeting with the sponsor and the business analyst who performed the business case before setting up a kickoff meeting.
Why did the project manager request the meeting?
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?
A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?
A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.
What should the project manager do?
A project team consists of several consultants from an external vendor. These consultants often change from month to month.
What should the project manager do to communicate the organizational values?
A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?
A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.
What should the project manager do first?
A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.
What should the project manager do?
A project team is using a vendor solution. The project team has been notified that the vendor solution will no longer be on the premises, but in the cloud. The cloud transition will require additional infrastructure resources and adherence to new security standards.
What should the project manager do first?
As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?
A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.
What should the project manager have done to avoid this situation?
A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team
requests a change in the sprint goals and sprint backlog items.
What should the project manager do?
A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?
An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.
What should the project manager do first?
A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.
What should the project manager do next?
A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.
What should the project manager do?
At the end of the last iteration, the customer rejects the deliverables since they did
not meet the customer's expectations. What should the project manager have been done
to prevent this situation?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.
What should the project manager do?
Close to the end of a project, a customer claims that some deliverables have not
been met and starts initiating change requests. What should the project manager do next?
The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors
What should the project manager do?
A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.
What should the project manager do?
A project manager is working on a large project with a very difficult client. During
the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.
How should the project manager approach this?
A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.
What strategy should the project manager implement to deal with this situation?
As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.
What should the project manager do?
A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
A product owner has an idea for a new product but is struggling to define the
features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?