Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (2025 Version) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMP Project Management Professional (2025 Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 11
Total 2040 questions

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?

A.

Provide clear expectations around task requirements.

B.

Review the task list with the team on a regular basis,

C.

Provide templates for the product owner to use in the future.

D.

Review the task with the sponsor to see if they are satisfied.

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

A.

Create a risk probability matrix to address the incompatibility.

B.

identify an alternative component in case of incompatibility.

C.

Use the contingency fund to redesign the interface if it is incompatible,

D.

Require the vendor to redesign the incompatible component to fit the system.

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

A.

Colocate the team members

B.

Perform team-building activities

C.

Review and reassign tasks

D.

Revisit the communications management plan

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

A.

Include the local union representative in the high-power, high-impact stakeholder group

B.

Focus on the sideward stakeholders only and let the organization manage the community.

C.

Build channels to extend communication efforts to the local community

D.

Use the city administration to address communication with the community

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

A.

Request help from human resources to keep the key team members on the project.

B.

Work with the project sponsor to determine an appropriate response.

C.

Ask to meet privately with the senior-level executive to discuss the matter further.

D.

Discuss the incident with the key project team members.

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

A.

Schedule a meeting with the director to provide proof of expertise so the clientstakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to acceptthe director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for thedecision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for thedecision.

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?

A.

Include this topic in the next iteration retrospective

B.

Review this topic with the product owner before the next iteration planning

C.

Discuss this topic with the team in the next daily meeting

D.

Ask the product owner to review this topic in the next iteration planning

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) andrequest that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

A.

Review the stakeholder engagement plan.

B.

Review the communications management plan.

C.

Send the CEO one executive summary per week instead of five reports per week.

D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on theproject variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

A.

Evaluate the project risk and add external experts to address the potential risks.

B.

Inform the project sponsor about the risk and try to convince them to withdraw from the project.

C.

Continue executing the project as planned and add more resources if they are required.

D.

Review the lessons learned on similar projects so that they do not fall back into the same pattern.

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client isnot impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

A.

Accept the change request from country A and reschedule the deployment project for country A.

B.

Take the request into account and ask the sponsor to inform countries B and C about the change

C.

Ask country A to submit a change request that will be analyzed along with countries B and C

D.

Refuse country As request as there is no time for the change as deployment has already begun

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and culturalobservance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overallproject governance.

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Page: 1 / 11
Total 2040 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved