Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMP PMI Project Management Professional (PMBOK 7th Version) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMP Project Management Professional (PMBOK 7th Version) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 11
Total 2191 questions

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives

B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders

C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project

D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

A.

Communicate the delivery dates twice a week to the team members to ensure timelydelivery.

B.

Set up review sessions with each of the team members to identify the root cause ofdelays.

C.

Mentor the team members to work in a remote work environment to ensureproductivity.

D.

Talk to the resource managers regarding the delay and request additional resources

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

A.

Submit a change request to include the manual.

B.

Add the needed manual and update the risk log.

C.

Review the stakeholder engagement plan.

D.

Review the terms and conditions of the contract.

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

A.

Add the situation to the project risk register to be managed

B.

Identify competitors that are qualified to replace the current supplier

C.

Inform the purchasing department that manages the supplier relationship

D.

Use the issue log to record the situation immediately

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?

A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer

B.

Meet with the risk manager to identify potential threats related to the schedule delay.

C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product

D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

A project manager submits several requests to purchase required hardware and

knows from previous experience that this kind of procurement usually results in disputes

between the company and its suppliers. How can the project manager mitigate this risk in the

request for proposal (RFP) with suppliers?

A.

Ask the legal team to review the RFP.

B.

Ask the project team to submit the RFP.

C.

Request approval of the RFP from the project sponsor.

D.

Request approval of the RFP from management.

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

A.

Define clear guidelines on how decisions should be made under the neworganizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance ofaccountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up theteam's velocity.

During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.

In order to reach a consensus and have a successful project completion, what should the

project manager do first?

A.

Analyze the bounds of the negotiation for agreement with both parties.

B.

Identify and satisfy both parties' underlying wants.

C.

Comply with the customer's request to achieve the project mandate.

D.

Initiate a change request to accommodate the revised cost of goods

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

A.

Include the issue in the risk register and update the team

B.

Document the continuing issue and failed solution

C.

Inform the stakeholders about the failure and update the issue log

D.

Meet with the project team to find another solution

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

A.

Company's historical organizational project artifacts

B.

Company's project responsibility assignment matrix (RAM)

C.

Company's resource management plan

D.

Company's resource calendars

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatoryrequirements.

D.

The project manager must follow their employer's organizational process assets(OPAs).

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?

A.

Inform executive management that the customer is made aware of the status duringthe sprint demo.

B.

Prepare a weekly status report and share it with executive management every week.

C.

Inform executive management about agile principles and processes that are followedin the project.

D.

Ask the team to prepare and share the status report with executive management everyweek.

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

A.

Implement daily standups where the team can share their impediments, risks, andissues.

B.

Review the communications management plan and implement changes.

C.

Schedule weekly risk review meetings with the team to review project risks andconcerns.

D.

Distribute a copy of the communications management plan to the scrum master.

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

A.

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

A.

Perform collaborative work that is coordinated by the project manager.

B.

Rely on the expert judgment of the product owner.

C.

Use a market-based strategy.

D.

Engage the project sponsor.

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.

Issue a change request to include the additional scope, and track the completion of the work items.

C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.

Arrange to pass the cost to the operational area since the customer will benefit.

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

A.

Request the project team include the stakeholder's details and make sure the projectstatus reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register forincorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

A.

Request to meet with the team member and ask that any issues be escalated separately.

B.

Reprimand the team member and provide immediate coaching on goal alignment.

C.

Proceed with defining the goals with the team members given the majority approval from the team.

D.

Approach the team member with empathy and obtain agreement through collaboration.

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

A.

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Page: 7 / 11
Total 2191 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved