Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PgMP PMI Program Management Professional (PgMP) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PgMP Program Management Professional (PgMP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 7
Total 452 questions

You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

A.

Quality control

B.

Benefits management

C.

Direct and manage program execution

D.

Quality assurance

Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?

A.

Close the constituent projects before closing the program

B.

Complete the program's budget

C.

Release the program's resources

D.

Sign the certificate of program closure

You are the program manager for your organization. Your current program has a budget at completion of

$3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

A.

$2,656,500

B.

There is not enough information to know. C. $3,795,000

C.

$1,035,000

A knowledge area defines a subset of program management and its processes within that

domain. For example, the knowledge area of quality management includes the processes related directly to quality management only. Which knowledge area ensures that all knowledge areas interact correctly with one another?

A.

Program benefits management

B.

Program management planning

C.

Integration management

D.

Communications management

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?

A.

Accelerate the projects and components of the program that replace the two legacy systems.

B.

Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor.

C.

Identify the parts of the program that need to be accelerated and, if it is cost effective and increases benefits realization, implement the change.

D.

Create several "what-if" scenarios of alternatives to present to the program sponsor.

Thequality assurance technique ensures continuous improvement of all processes.

A.

Just-in-time management

B.

Ishikawa

C.

Six Sigma

D.

Kaizen

A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.

What should the program manager do to address these key stakeholders' concerns?

A.

Meet with the stakeholders and update the stakeholder map.

B.

Create a progress report to share with stakeholders after the next status meeting.

C.

Capture stakeholder expectations, and revise the stakeholder engagement plan.

D.

Update the communications management plan after meeting with the program steering committee.

Who prepares the statement of work (SOW) for external projects?

A.

Customer

B.

Project management team

C.

Project Manager

D.

Chief Financial Officer (CFO)

At what point in the project is the risk of failing to achieve the project objectives the greatest?

A.

During project planning

B.

During the project execution

C.

At the project start

D.

At the end of the project

A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board’s expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.

How should the program manager handle this situation?

A.

Review the final program outcome with the program sponsor

B.

Prepare a program change request utilizing new board member input

C.

Review the strategic plan and benefits management plan with the board

D.

Present the final program status, costs, and schedule reports

The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent projects and components to meet the program's needs.

What action should the program manager take to realign the program?

A.

Assess the program schedule and determine how to maintain all projects and components within the program.

B.

Discuss the situation with the program stakeholders and let them decide which projects to accelerate and which to close.

C.

Discuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to which projects to accelerate and which to close.

D.

Develop a change request to present to the governance board, accelerate some projects, close some projects, and reassign some resources.

Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?

A.

Project Integration Plan

B.

Project Contract

C.

Project Quality Control procedures

D.

Project Communications Management Plan

How does a portfolio’s collection of work differ from that of a program’s collection of work?

A.

Outcomes are interdependent

B.

Benefits are achieved only when managed collectively

C.

Components may be independent

D.

Outcomes are time bound

An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?

A.

$2,322,481

B.

$1,950,000

C.

$2,067,000

D.

$1,950,001

A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component project requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.

What is a critical component of the Program Schedule Management Process?

A.

A list of all the projects that team members are working on

B.

Activity or component start and finish dates, as well as intermediate milestones

C.

Time management training programs for all team members, as well as the project managers

D.

Skill levels of the various project team members, as well as the project managers

Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

A.

Project managers

B.

Hans

C.

Program director

D.

Hans and each project manager

You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?

A.

Requirements technical documentation

B.

Project scope statement

C.

Project charter

D.

Detail design document

You are the program manager for your organization and you are trying to determine the possible outcomes of

a risk event. You're analyzing the risk event's worst case scenario, most likely scenario, and optimistic scenario to simulate the possible affects of the risk on the program's cost, time, and scope ramifications. What simulation technique are you using in this situation?

A.

Monte Carlo simulation

B.

Sensitivity analysis

C.

Force field analysis

D.

Decision tree analysis

As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

A.

The project management lifecycle and the project lifecycle are the same thing.

B.

The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work.

C.

The project management lifecycle is unique to each project while the project lifecycle is universal to all projects.

D.

The project management lifecycle is universal to all projects and the project lifecycle is unique to each project.

You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?

A.

Payback period

B.

Cost performance index

C.

Cost-to-benefits ratio

D.

Return on investment

Page: 4 / 7
Total 452 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved