PgMP PMI Program Management Professional (PgMP) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PgMP Program Management Professional (PgMP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 7
Total 452 questions

A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

A.

Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered

B.

Host a kick-off meeting; request preliminary requirements from the marketing department; conduct a design session; present the steering committee with a solution that meets the requirements; and meet with interested vendors

C.

Ask a senior marketing executive to act as the program sponsor and participate on the steering committee; require steering committee representation from the IT, legal, and other key departments; validate that the chosen solution meets the requirements

D.

Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gain the confidence of the legal department

Complete the following phrase about quality management: Quality isinto a program, notinto a program.

A.

Built, inspected

B.

Planned, inspected

C.

Planned, controlled

D.

Executed, controlled

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

A.

Project Management Information System

B.

Integrated Change Control

C.

Scope Verification

D.

Configuration Management System

A company hires a program manager to create a healthcare management system. After five months, the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

A.

Critical success factors

B.

Key performance indicators

C.

Benefits management plan

D.

Stakeholder engagement plan

An unforeseen geopolitical risk impacts a program to establish a company’s operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.

What should the program manager recommend to stakeholders for future, similar situations?

A.

Accept the risk

B.

Seek an expert opinion

C.

Establish an on-call risk response team

D.

Review the risk severity matrix

You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of

the schedule control process except for which one?

A.

Stakeholder communication information

B.

Schedule variances

C.

Program schedule updates

D.

Change requests

The new performance financial system is delivered to all business entities on time following a one-year

implementation program. After six months of utilization the global finance department, one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined. Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies.

To address these shortcomings, the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

A.

Benefits sustainment plan

B.

Benefits governance plan

C.

Benefits realization report

D.

Benefits transition plan

Andy is the program manager of the HQN Program. This program is nearing its completion and there is still

$25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

A.

Value-added change requests

B.

Zero based budgeting

C.

Integrated change control

D.

Gold plating

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template, while others prefer another.

How should the program manager decide which template is appropriate?

A.

Review the issue with the program management office (PMO) to determine which template to use.

B.

Review the issue with the project managers and come to mutual agreement on which template to use.

C.

Meet with the program governance board to select an appropriate template.

D.

Allow the component project managers to use their preferred templates.

You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any QUESTION NO:s the vendors may have about the project. What is this meeting called?

A.

Sales meeting

B.

Select sellers process

C.

Bidder conference

D.

Negotiations

Which of the following documents describes the details for each component in the WBS?

A.

WBS detail

B.

Risk register

C.

WBS dictionary

D.

Project charter

A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.

What should the program manager do first?

A.

Update the benefits management plan, and send it to stakeholders for review.

B.

Document the impact on the program, then present the findings to the steering committee to determine next steps.

C.

Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.

D.

Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.

Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?

A.

Earned Value Management report on the schedule performance index

B.

Exceptions report

C.

Status report

D.

Quality Control Report

You are identifying stakeholders for your program to create new software for your organization. The software will affect the ordering by the customer, the manufacturing of the product, inventory, and account management. Sarah, a key stakeholder in your program, is skeptical of one application affecting so many parts of the organization. She prefers that several applications be created instead of the approach your program will take. In stakeholder identification how would you categorize Sarah?

A.

Active

B.

Negative

C.

Positive

D.

Passive

A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

A.

Develop the benefits sustainment plan.

B.

Develop the program management plan.

C.

Develop the program roadmap.

D.

Develop the component project schedules.