PMI-001 PMI Project Management Professional v5 Free Practice Exam Questions (2025 Updated)
Prepare effectively for your PMI PMI-001 Project Management Professional v5 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
The correct equation for schedule variance (SV) is earned value:
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
A weighting system is a tool for which area of procurement?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
The cost of nonconformance in a project includes:
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
The following is a network diagram for a project.
The total float for the project is how many days?
Which is an example of Administer Procurements?
Which of the following are inputs to Activity Definition?
The lowest level normally depicted in a work breakdown structure (WBS) is called a/an:
The process of identifying the stakeholders' information needs is completed during:
"Tailoring" is defined as the:
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
The milestone list is an input to which process from the Planning Process Group?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A reward can only be effective if it is:
Which of the following is a complete set of indexed contract documentation, including the closed contract?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
The procurement process that documents agreements and related documentation for future reference is known as:
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
In a weak matrix, the project managers role is:
What do composite organizations involve?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
Which of the following is a tool or technique of the Define Activities process?
The process of formalizing acceptance of the completed project deliverables is known as:
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
When sequencing activities, what does the common acronym FF stand for?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Exhibit A is an example of which of the following types of Sequence Activities?
An example of a group decision-making technique is:
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
An input of the Plan Procurement Management process is:
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
What quality control tool graphically represents how various elements of a system interrelate?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
An output of the Develop Project Team process is:
An output of the Validate Scope process is: