C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Free Practice Exam Questions (2025 Updated)

Prepare effectively for your SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 3
Total 165 questions

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:

A.

Internally-processed activities

B.

Externally-processed activities

C.

Service activities

D.

Scheduled activities

Which of the following determines the item category assigned in the sales documents?

There are 2 correct answers to this question.

Response:

A.

Sales document type

B.

Schedule line items

C.

Material pricing group

D.

Material item category group

Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?

Please choose the correct answer.

Response:

A.

Cost indicators

B.

Project cost indicators

C.

Operative indicators

D.

Billing indicators

Can the user status forbid business transactions that the system status allows?

Please choose the correct answer.

Response:

A.

No, user status can only create a warning.

B.

Yes, by creating an appropriate status profile.

C.

Yes, if the status number of the user status is defined with higher priority.

D.

No, system status has a higher priority than user status.

What is the transaction code for editing the planning profile?

Please choose the correct answer.

Response:

A.

OPSS

B.

OPDS

C.

OPSB

D.

OPSC

Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?

Please choose the correct the answer.

Response:

A.

Hierarchical Reports

B.

Individual Overviews

C.

Reports by Cost Element

D.

Structure Overview

Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?

Please choose the correct answer.

Response:

A.

Progress analysis

B.

Cost forecasts

C.

Overhead costs

D.

Interest forecast

Which of the following statements concerning ProMan are correct? (5)

A.

To use ProMan, you must have defined the corresponding profiles in Customizing

B.

In ProMan, you can also analyze purchase orders that have been manually account-assigned to a WBS element

C.

You can define user-specific layouts for the overviews in ProMan

D.

In ProMan, you can also post goods receipts and goods issues among other things.

E.

In the Customizing profile for ProMan, you can specify which exceptions are displayed, which orders and documents are read and which views are displayed

F.

In ProMan, you cannot only analyze data from the Project System but also data from Materials Management, Purchasing and Production

What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

There are 2 correct answers to this question.

Response:

A.

The "project stock" indicator is set in the project definition (either valuated or non-valuated)

B.

The "Valuated project stock" indicator must be set in the project definition.

C.

The MRP group of the components must permit requirements grouping.

D.

The project must be released.

E.

The top-level WBS element must be released.

Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders?

Please choose the correct answer.

Response:

A.

C

B.

B

C.

F

D.

E

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

A.

Periodic settlement

B.

Full settlement

C.

Profile settlement

D.

Overview settlement

Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

Please choose the correct answer.

Response:

A.

Trend technique

B.

Project technique

C.

Milestone technique

D.

Period indicator technique

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?

Please choose the correct answer.

Response:

A.

Deviations

B.

Time gaps

C.

Floats

D.

High priority

If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?

There are 2 correct answers to this question.

Response:

A.

Plant stock

B.

Project stock

C.

General stock

D.

Sales order stock

Which of the following type determines which type of orders a system can create during assembly processing?

Please choose the correct answer.

Response:

A.

Assembly type

B.

Order type

C.

Account assignment category

D.

Item type

Project System has its own Organizational structure, which can be a matrix structure.

Please choose the correct answer.

Response:

A.

True

B.

False

Which account assignment category is important for non-valuated project stock with WBS and sales order item?

Please choose the correct answer.

Response:

A.

E = quantities and values managed in the sales order item

B.

D = quantities managed using sales order item and values managed in projects

C.

G = plant stock, values managed using projects

D.

Q = quantities and values managed in projects

How do you derive the hierarchy of a work breakdown structure from the numbers of their WBS elements?

Please choose the correct answer.

Response:

A.

Standard structures

B.

Coding masks

C.

WBS element fields

D.

Operative structures

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?

Please choose the correct answer.

Response:

A.

The control key is set to no scheduling.

B.

The scheduling type is set to capacity requirements only.

C.

The normal duration of each activity is missing.

D.

There is a loop in the network.

Based on which of the following; reservations or purchase requisitions can automatically be created for a project?

There are 2 correct answers to this question.

Response:

A.

WBS element

B.

Internal service planning

C.

External service planning

D.

Material

Page: 2 / 3
Total 165 questions