Prepare effectively for your SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
What happens if the appended indicator is not set and an order is appended?
Please choose the correct answer.
Response:
When using budgeting and active availability control, which business transactions affect the current budget?
There are 3 correct answers to this question.
Response:
Which of the following items can be included in the planned costs for an activity besides the cost of the activity?
There are 3 correct answers to this question.
Response:
In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?
There are 2 correct answers to this question.
Response:
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities?
Please choose the correct answer.