Prepare effectively for your SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 3
Total 165 questions

Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?

There are 3 correct answers to this question.

Response:

A.

WBS element

B.

Assignment

C.

Network header

D.

Network activity

What is copied when transferring a simulation version back to an operative project?

There are 3 correct answers to this question.

Response:

A.

Plan costs

B.

WBS elements

C.

Actual work

D.

Maintenance orders assigned to the project

E.

Network activities

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?

There are 2 correct answers to this question.

Response:

A.

Billing element

B.

Cost element

C.

Pricing element

D.

Account assignment element

Where can you define that a network is a "header-account assigned" or "activity-account assigned"?

A.

Network profile

B.

Parameters for the network type

C.

Project profile

D.

Network type

What is the starting point for milestone billing?

Please choose the correct answer.

Response:

A.

Purchase requisition

B.

Purchase order

C.

Goods receipt

D.

Sales order item with a billing plan

Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?

Please choose the correct answer.

Response:

A.

Stock item

B.

Network item

C.

Non-stock item

D.

Procurement item

Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?

Please choose the correct answer.

Response:

A.

Costing variant

B.

Valuation variant

C.

Planned cost variant

D.

Network variant

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Which of the following can be used to calculate and update interest in SAP project system?

There are 2 correct answers to this question.

Response:

A.

Planned interest calculation

B.

Actual interest calculation

C.

Compound interest calculation

D.

Result analysis

Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

Please choose the correct answer.

Response:

A.

Scheduled orders

B.

Procurement orders

C.

Planned orders

D.

Stock orders

Which type of confirmation allows you to confirm various networks, activities, activity elements, and individual capacities at the same time?

Please choose the correct answer.

Response:

A.

Open PS interface

B.

Collective confirmation

C.

Structure information system

D.

CATS

When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?

There are 2 correct answers to this question.

Response:

A.

WBS elements

B.

Sales orders

C.

Settlement rules

D.

Result analysis

Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?

Please choose the correct answer.

Response:

A.

Individual confirmation

B.

Single confirmation

C.

Collective confirmation

D.

Group confirmation

In which of the following is the Capacity planning Indicator set?

Please choose the correct answer.

Response:

A.

Control Key

B.

Work Center

C.

Requirement

D.

Task

While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?

Please choose the correct answer.

Response:

A.

Scheduling forwards

B.

Scheduling backwards

C.

Variances

D.

Scheduling baseline, planned and forecast

Which of the following are controlled using plant and order type parameters?

There are 2 correct answers to this question.

Response:

A.

Number assignment

B.

If the network is assigned to an activity or header

C.

Default value settings

D.

The settlement rule strategy

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

Response:

A.

The system status created is active.

B.

The system status master data locked is activate.

C.

You are not the responsible person for that WBS element.

D.

The confirmation exceeds the budget assigned to the WBS.

You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...

There are 2 correct answers to this question.

Response:

A.

... basic dates of WBS elements are determined automatically.

B.

... the networks determine the schedule.

C.

... strict bottom-up planning is selected as the planning method.

D.

... forward scheduling is selected as the scheduling type.

E.

... the work breakdown structure determines the schedule.

You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.

What are the possible reasons for this?

There are 2 correct answers to this question.

Response:

A.

A work center has not been assigned to the activity.

B.

The work center does not contain any available capacity data.

C.

The wrong activity type category is entered in the activity.

D.

The indicator calculate capacity requirements is deactivated in the header of the network.

What do you choose when creating a new network by copying an operative network?

There are 3 correct answers to this question.

Response:

A.

PS texts

B.

Relationships

C.

Milestones

D.

WBS elements