C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Free Practice Exam Questions (2025 Updated)
Prepare effectively for your SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?
There are 3 correct answers to this question.
Response:
What is copied when transferring a simulation version back to an operative project?
There are 3 correct answers to this question.
Response:
To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:
Where can you define that a network is a "header-account assigned" or "activity-account assigned"?
What is the starting point for milestone billing?
Please choose the correct answer.
Response:
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?
Please choose the correct answer.
Response:
Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?
Please choose the correct answer.
Response:
In which of the following levels can you execute BOM transfer in the order browser?
There are 3 correct answers to this question.
Response:
Which of the following can be used to calculate and update interest in SAP project system?
There are 2 correct answers to this question.
Response:
Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?
Please choose the correct answer.
Response:
Which type of confirmation allows you to confirm various networks, activities, activity elements, and individual capacities at the same time?
Please choose the correct answer.
Response:
When the system derives settlement rules, it generates profitability segments that contain the characteristic values of which of the following assigned to them?
There are 2 correct answers to this question.
Response:
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
In which of the following is the Capacity planning Indicator set?
Please choose the correct answer.
Response:
While customizing the progress tracking profile which indicator specifies whether the respective dates are to be scheduled?
Please choose the correct answer.
Response:
Which of the following are controlled using plant and order type parameters?
There are 2 correct answers to this question.
Response:
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.
Response:
You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...
There are 2 correct answers to this question.
Response:
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:
What do you choose when creating a new network by copying an operative network?
There are 3 correct answers to this question.
Response: